New utilities Sample Clauses

New utilities. (i) The Contractor shall allow, subject to the permission from the Authority and such conditions as the Authority may specify, access to, and use of the Site for laying telephone lines, water pipes, electricity lines/ cables or other public utilities. Where such access or use causes any financial loss to the Contractor, it may require the user of the Site to pay compensation or damages as per Applicable Laws. For the avoidance of doubt, it is agreed that use of the Site under this Clause 9.3 shall not in any manner relieve the Contractor of its obligation to construct and maintain the Project Highway in accordance with this Agreement and any damage caused by such use shall be restored forthwith at the cost of the Authority.
AutoNDA by SimpleDocs
New utilities. The Concessionaire shall allow, subject to such conditions as the Authority may specify, access to, and use of the Site for laying telephone lines, water pipes, electric cables or other public utilities. Where such access or use causes any financial loss to the Concessionaire, it may require the user of the Site to pay compensation or damages as per Applicable Laws. For the avoidance of doubt, it is agreed that use of the Site under this Clause 11.3 shall not in any manner relieve the Concessionaire of its obligation to maintain the Port in accordance with this Agreement and any damage caused by such use shall be restored forthwith.
New utilities. The Mine Developer and Operator shall allow, subject to such conditions as TANGEDCO may specify, access to, and use of the Site for laying telephone lines, water pipes, electric cables or other public utilities, but only if it does not affect the operations of the Mines. Where such access or use causes any financial loss to the Mine Developer and Operator, it may require the user of the Site to pay compensation or as per Applicable Laws. For the avoidance of doubt, it is agreed that use of the Site under this Clause 11.3 shall not in any manner relieve the Mine Developer and Operator of its obligation to operate and maintain the Mines in accordance with this Agreement and any Damage caused by such use shall be restored forthwith by the Mine Developer and Operator.
New utilities. DB Contractor shall be entitled to a Change Order: (a) increasing the Price to compensate DB Contractor for any increase in DB Contractor’s costs incurred in performing the Utility Adjustment Work that is directly attributable to a New Utility (including reimbursements owed to Utility Owners but excluding delay and disruption damages), and (b) extending the applicable Completion Deadline as a result of any delay in the Critical Path directly attributable to performing the Utility Adjustment Work directly attributable to a New Utility. DB Contractor shall keep records of its costs related to New Utilities separate from other costs. Subject to the foregoing, the amount of such Change Order shall be determined in accordance with Section 13.
New utilities. 9.3.1 The Contractor shall allow, subject to such conditions as the Employer may specify, access to, and use of the Site for laying telephone lines, water pipes, electric cables or other public utilities. Where such access or use causes any financial loss to the Contractor, it may require the user of the Site to pay compensation or damages as per Applicable Laws. For the avoidance of doubt, it is agreed that use of the Site under this Clause 9.3 shall not in any manner relieve the Contractor of its obligation to construct and maintain the Project Works in accordance with this Agreement and any damage caused by such use shall be restored forthwith at the cost of the Employer. For details please refer Schedule B.
New utilities. Developer shall be entitled to a Change Order: (i) increasing the Price to compensate Developer for any increase in Developer’s costs incurred in performing the Utility Adjustment Work that is directly attributable to a New Utility (including reimbursements owed to Utility Owners but excluding delay and disruption damages), and (ii) extending the applicable Completion Deadline as a result of any delay in the Critical Path directly attributable to performing the Utility Adjustment Work directly attributable to a New Utility. Subject to the foregoing, the amount of such Change Order shall be determined in accordance with Section 12.
New utilities. DB Contractor shall be entitled to a Change
AutoNDA by SimpleDocs
New utilities. Developer shall be entitled to a Change Order:
New utilities. DB Contractor shall be entitled to a Change Order:
New utilities. 9.3.1 The Contractor shall allow, subject to such conditions as the Authority may specify, access to, and use of the Site for laying telephone lines, water pipes, electric cables or other public utilities. Where such access or use causes any financial loss to the Contractor, it may require the user of the Site to pay compensation or damages as per Applicable Laws. For the avoidance of doubt, it is agreed that use of the Site under this Clause 9.3 shall not in any manner relieve the Contractor of its obligation to construct the Project in accordance with this Agreement and any damage caused by such use shall be restored forthwith at the cost of the Authority.