Synchronisation Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Synchronisation Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM BESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Appears in 2 contracts
Synchronisation Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty fourty five (40) days advanced preliminary written notice and at least twenty (2045) days advanced final written notice to ESCOM BESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
Appears in 1 contract
Samples: Power Purchase Agreement