AND LIQUIDATED DAMAGES Sample Clauses

AND LIQUIDATED DAMAGES. G-1 INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ....... G-3 NO MAJOR CONTRACT ITEMS:............................................................................................ G-3 NO SPECIALTY ITEMS: .......................................................................................................... G-3 SCHEDULE OF ESTIMATED COMPLETION PROGRESS:................................................. G-4 DISADVANTAGED BUSINESS ENTERPRISE: .................................................................... G-4 CERTIFICATION FOR FEDERAL-AID CONTRACTS: ...................................................... G-17 U.S. DEPARTMENT OF TRANSPORTATION HOTLINE: ................................................. G-18 CARGO PREFERENCE ACT: ................................................................................................ G-19 LOCATING EXISTING UNDERGROUND UTILITIES:...................................................... G-19 VALUE ENGINEERING PROPOSAL: .................................................................................. G-19 RESOURCE CONSERVATION AND ENV. SUSTAINABLE PRACTICES:...................... G-21 DOMESTIC STEEL: ................................................................................................................ G-21 MAINTENANCE OF THE PROJECT: ................................................................................... G-22 TWELVE MONTH GUARANTEE:........................................................................................ G-22 GIFTS FROM VENDORS AND CONTRACTORS: .............................................................. G-23 LIABILITY INSURANCE:...................................................................................................... G-24 EMPLOYMENT:...................................................................................................................... G-24 STATE HIGHWAY ADMINISTRATOR TITLE CHANGE:................................................. G-24 SUBLETTING OF CONTRACT: ............................................................................................ G-24 ROADWAY................................................................................................................................ R-1
AutoNDA by SimpleDocs
AND LIQUIDATED DAMAGES. G-1 INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ....... G-2 INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES: ....... G-3 MAJOR CONTRACT ITEMS: .................................................................................................. G-3 SPECIALTY ITEMS: ................................................................................................................. G-3 FUEL PRICE ADJUSTMENT:.................................................................................................. G-4 SCHEDULE OF ESTIMATED COMPLETION PROGRESS:................................................. G-4 DISADVANTAGED BUSINESS ENTERPRISE: .................................................................... G-5 CERTIFICATION FOR FEDERAL-AID CONTRACTS: ...................................................... G-17 CONTRACTOR'S LICENSE REQUIREMENTS: .................................................................. G-18 U.S. DEPARTMENT OF TRANSPORTATION HOTLINE: ................................................. G-18 CARGO PREFERENCE ACT: ................................................................................................ G-19 MAINTENANCE OF THE PROJECT: ................................................................................... G-19 EROSION AND SEDIMENT CONTROL/STORMWATER CERTIFICATION: ................. G-20 PROCEDURE FOR MONITORING BORROW PIT DISCHARGE:..................................... G-25 ROADWAY................................................................................................................................ R-1
AND LIQUIDATED DAMAGES. (5-21-13) 108 SP1 G14 I The Contractor shall complete the work required of installing each new inductive loop after the removal of each existing loop by the milling, patching or resurfacing operations and shall place and maintain traffic on same. The date of availability for this intermediate contract time for each inductive loop installation will be the date when the Contractor elects to disturb the existing inductive loop. The completion date for this intermediate contract time for each inductive loop installation will be the date which is seven (7) consecutive calendar days after the date of availability. The liquidated damages are Five Hundred Dollars ($ 500.00) per calendar day.
AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 A The Contractor shall complete the required work of installing, maintaining, and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow a lane of traffic on ANY ROAD during the following time restrictions: In addition, the Contractor shall not close or narrow a lane of traffic on ANY ROAD, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
AND LIQUIDATED DAMAGES. G-1 INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ....... G-3 INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES: ....... G-3 INTERMEDIATE CONTRACT TIME NUMBER 4
AND LIQUIDATED DAMAGES. (07-11-17) 108 The Contractor shall begin work at the site of emergency mobilization within 2 hours after notification or as determined by the Engineer. The liquidated damages for this intermediate contract time are Five Hundred Dollars ($ 500.00) per hour, per notification. (06-01-16) SPD 01-420B The provisions of Articles 102-10 and 103-7 of the 2012 Standard Specifications for Roads and Structures are waived for this project. No bonds required.
AND LIQUIDATED DAMAGES. (07-11-17) 108 The Contractor shall begin work at the site of routine mobilization within 5 days after notification or as determined by the Engineer. The liquidated damages for this intermediate contract time are Five Hundred Dollars ($ 500.00) per calendar day per notification.
AutoNDA by SimpleDocs
AND LIQUIDATED DAMAGES. (2-20-07) (Rev. 6-26-19) 108 SP1 G14 G (Rev.) The Contractor shall complete the work required of milling and resurfacing adjacent lanes and/or ramp areas in the same direction simultaneously (to limit differences in elevation prior to the next day’s milling and resurfacing operations) as shown on Any Map and shall place and maintain traffic on same. The time of availability for this intermediate contract time is the time the Contractor begins the work. The completion time for this intermediate contract time is the time which is seventy-two (72) consecutive hours after the Contractor begins this work. The liquidated damages are Two Thousand Dollars ($ 2,000.00) per calendar day.
AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for road closures and restoring traffic to the existing traffic pattern. The Contractor shall not close any I-40 Single-lane ramp or loop during the following time restrictions: The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern The liquidated damages are One Thousand Two Hundred and Fifty Dollars ($ 1,250.00) per
AND LIQUIDATED DAMAGES. (6-18-13) (Rev. 6-26-19) 108 SP1 G14 K (Rev.) On Maps #1 and #2, any newly placed ACSC Type S9.5D shall not remain uncovered by OGAFC more than sixty (60) days. The Contractor’s progression within these maps, considering this restriction, shall be at his/her discretion. The date of availability for this intermediate contract time is the date that ACSC Type S5.9D is placed in any given location within the map. The completion date for this intermediate contract time is the date that is sixty (60) consecutive calendar days after the date of availability. The liquidated damages are Two Thousand Dollars ($ 2,000.00) per calendar day.