Anticipated Project Schedule Clause Samples
POPULAR SAMPLE Copied 1 times
Anticipated Project Schedule. Site Visit – Early April 2021.
Anticipated Project Schedule. The schedule will be verified upon approval of the Schematic Design and phasing plans. The following project milestones as referenced in Section 1.1.1 and Section 1.1.2 are as follows:
Anticipated Project Schedule. 1. PEC shall commence its services on the Project within 7 days after receiving Client’s notice to proceed.
2. PEC and Client anticipate that the design duration to complete construction documents will be approximately 3 months after receiving Notice to Proceed. The design schedule is dependent on the Planning requirements of the City of ▇▇▇▇▇▇▇▇.
3. Client acknowledges that directed changes, unforeseen conditions, and other delays may affect the completion of PEC’s services. PEC will not have control over or responsibility for any contractor or vendor’s performance schedule.
4. Project deliverable schedules will be impacted by untimely receipt of information.
Anticipated Project Schedule. 1. The fully executed copy of the contract will serve as PEC’s notice to proceed with the services.
2. PEC shall commence its services on the PROJECT within fourteen (14) days after receiving CLIENT’s notice to proceed.
3. PEC and CLIENT anticipate the Preliminary Site Discovery and Conceptual Master Plan services to be completed approximately three (3) months after receiving CLIENT’s notice to proceed.
4. CLIENT acknowledges that directed changes, unforeseen conditions, and other delays may affect the completion of PEC’s services. PEC will not have control over or responsibility for any contractor or vendor’s performance schedule.
Anticipated Project Schedule. Anticipated timeline for completing the Project in accordance with the estimated project budget.
Anticipated Project Schedule. The anticipated project schedule, included as Attachment 2, assumes approval of an Interlocal Agreement between the City and TCRPC in October, with project initiation in October 2020 and completion in May 2021. The schedule identifies tasks, lead entity (e.g., TCRPC, City staff), and anticipated timeframe for completion of work.
Anticipated Project Schedule. The following is an outline of the anticipated schedule for the proposal review and contract award. Schedule is subject to change. March 19, 2021 Issue Request for Proposal (RFP) March 31, 2021 Pre-Proposal Meeting April 12, 2021 Intent to Propose Due April 26, 2021 12:00 PM Question Period Ends April 30, 2021 Addendum Issued (if needed) May 19, 2021 @ 4:00 PM Proposals Due May 20-26, 2021 Evaluation Period June 10, 2021 Make Recommendation TBD NTP ▇▇▇▇▇▇ ▇▇▇▇▇▇▇, Buyer ▇▇ ▇ ▇▇▇▇▇▇▇▇ ▇▇▇. Ste. 106 Meridian, ID 83642 (▇▇▇) ▇▇▇-▇▇▇▇ Fax (▇▇▇) ▇▇▇-▇▇▇▇ Dated:
Anticipated Project Schedule. The following is an outline of the anticipated schedule for the proposal review and contract award. Schedule is subject to change. February 27, 2022 March 9, 2022 March 14, 2022 12:00 PM March 16, 2022 March 23, 2022 4:00 PM March 25-April 4, 2022 April 8, 2022 TBD
Anticipated Project Schedule. 1. The fully executed copy of the contract will serve as PEC's notice to proceed with the services.
2. PEC shall commence its services on the Project within fourteen (14) days after receiving CLIENT’s notice to proceed.
3. PEC and CLIENT anticipate design duration for the roadway repairs will be approximately 30 days. Respectively, after receiving the Notice to Proceed.
4. Construction duration is anticipated to be 75 Calendar Days to Substantial Completion (SC) and 90 Calendar Days to Final Completion (FC). PEC anticipates the notice to proceed for construction to be issued approximately March 17, 2025 and for the PROJECT to be complete by June 14, 2025. The inspection services fee will be based on 90 calendar days.
5. CLIENT acknowledges that directed changes, unforeseen conditions, and other delays may affect the completion of PEC’s services. PEC will not have control over or responsibility for any contractor or vendor’s performance schedule.
Anticipated Project Schedule. 1. Wood shall commence its services on the supplemental scope within 7 days after receiving CLIENT’s notice to proceed.
2. Wood and CLIENT anticipate that the supplemental scope (excluding construction phase services) will be completed by June 30, 2021.
3. Client acknowledges that directed changes, unforeseen conditions and other delays may affect the completion of services by the above referenced time frame.