Availability of Lands. 4.1.1 County shall furnish, as indicated in the Contract Documents and no later than the date when needed by Contractor, access to the lands upon which the Work is to be done, right-of-way for access thereto, and such other lands which are designated for the use of Contractor. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by County, unless otherwise specified in the Contract Documents. If Contractor believes that any delay in County’s furnishing these lands or easements entitles it to an extension of the contract time, it may make a claim therefore as provided in Section 3.3.2 of the Construction Contract. County will provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of material and equipment as shown in the Contract Documents.