Black Start Services. 5.10.1 All Participating Generators with Black Start Generating Units must satisfy technical requirements specified by the ISO. 5.10.2 The ISO shall from time to time undertake performance tests, with or without prior notification. 5.10.3 The ISO shall have the sole right to determine when the operation of Black Start Generating Units is required to respond to conditions on the ISO Controlled Grid. 5.10.4 If the ISO has intervened in the market for Energy and/or Ancillary Services pursuant to Section 2.3.2.3, the price paid by the ISO for Black Start services shall be sufficient to permit the relevant Participating Generator to recover its costs over the period that it is directed to operate by the ISO. 5.10.5 If a Black Start Generating Unit fails to achieve a Black Start when called upon by the ISO, or fails to pass a performance test administered by the ISO, the relevant owner of Reliability Must-Run Unit shall re-pay to the ISO any reserve payment(s) that it has received since the administration of the last performance test or the last occasion upon which it successfully achieved a Black Start when called upon by the ISO, whichever is the shorter period.
Appears in 3 contracts
Samples: Transmission Control Agreement, Transmission Control Agreement, Transmission Control Agreement
Black Start Services. 5.10.1 All Participating Generators with Black Start Generating Units must satisfy technical requirements specified by the ISO.
5.10.2 The ISO shall from time to time undertake performance tests, with or without prior notification.
5.10.3 The ISO shall have the sole right to determine when the operation of Black Start Generating Units is required to respond to conditions on the ISO Controlled Grid.
5.10.4 If the ISO has intervened in the market for Energy and/or Ancillary Services pursuant to Section 2.3.2.3, the price paid by the ISO for Black Start services shall be sufficient to permit the relevant Participating Generator to recover its costs over the period that it is directed to operate by the ISO.
5.10.5 If a Black Start Generating Unit fails to achieve a Black Start when called upon by the ISO, or fails to pass a performance test administered by the ISO, the relevant owner of Reliability Must-Run Market Participant that has contracted to supply Black Start service from the Generating Unit shall re-pay to the ISO any reserve payment(s) that it has received since the administration of the last performance test or the last occasion upon which it successfully achieved a Black Start when called upon by the ISO, whichever is the shorter period.