Common use of Certificates for Payment to Contractor Clause in Contracts

Certificates for Payment to Contractor. § 3.6.3.1 The Architect shall review and certify an application for payment not more frequently than monthly. Within seven days after the Architect receives an application for payment forwarded from the Construction Manager, the Architect shall review and certify the application as follows:

Appears in 3 contracts

Samples: www.clarendonisd.net, static1.squarespace.com, www.southernplainsedcoop.org

AutoNDA by SimpleDocs

Certificates for Payment to Contractor. § 3.6.3.1 The Architect shall review and certify an application for payment not more frequently than monthly. Within truc Ar on M e the Contractor and shall rent ate fanag seven days after the Architect receives an application for payment forwarded from the Construction Manager, the Cons Architect shall review and certify the application as follows:

Appears in 1 contract

Samples: www.pbsd.net

Certificates for Payment to Contractor. § 3.6.3.1 The Architect shall observe the progress of the work, evaluate, review and certify an application for payment not more frequently than monthly. Within seven days after the Architect receives an application for payment forwarded from the Construction Manager, the Architect shall review and certify the application as follows:

Appears in 1 contract

Samples: www.westada.org

Certificates for Payment to Contractor. § 3.6.3.1 The Architect shall review and certify an application for payment not more frequently than monthly. Within seven days after the Architect receives an application for payment forwarded from the Construction Manager, and based on the Architect’s observations and on its evaluations of the Contractor’s Application for Payment, the Architect shall review and certify certify, or give the reasons for its refusal to certify, the application as follows:

Appears in 1 contract

Samples: www.newarkcsd.org

AutoNDA by SimpleDocs

Certificates for Payment to Contractor. § 3.6.3.1 The TheNot more frequently than monthly, the Architect shall review and certify an application for payment not more frequently than monthly. Within seven days after the Architect receives an application for payment forwarded from the Construction Manager, the Architect shall review and certify the application as follows:

Appears in 1 contract

Samples: content.aia.org

Certificates for Payment to Contractor. § 3.6.3.1 The Architect Architect, within seven (7) days of receipt of a payment application from the Contractor, shall review and certify an application for payment not more frequently than monthly. Within seven days after the Architect receives an application for payment forwarded from the Construction Manager, the Architect shall review and certify the application as followstake action by:

Appears in 1 contract

Samples: www.minnstate.edu