Common use of Claims for Delay Clause in Contracts

Claims for Delay. Where the Contractor deems that additional compensation or a time extension is due on account of delay, differing site conditions, breach of Contract, or any other cause other than for work or materials not expressly provided for in the Contract (Extra Work) or which is by written directive of the Engineer expressly ordered by the Engineer , the Contractor shall submit a written notice of intent to the Engineer within ten days after commencement of a delay to a controlling work item expressly notifying the Engineer that the

Appears in 3 contracts

Samples: Asset Maintenance Contract, Asset Maintenance Contract, Asset Maintenance Contract