CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 1.1.4, 6
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 6.1 Owner’s Right to Perform Construction and to Award Separate Contracts
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 6.1 OWNER'S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS
6.1.1 Owner reserves the right to perform construction or operations related to the Project with the Owner's own forces and to award separate contracts in connection with other portions of the Project or other construction of operations on the site under Conditions of the Contract identical, or substantially similar, to these including those portions related to insurance and waiver of subrogation. If the Contractor claims that delay or additional cost is involved because of such action by the Owner, the Contractor shall make such Claim as provided in Paragraph 4.3.
6.1.2 When separate contracts are awarded for different portions of the Project or other construction of operations on the site, the term "Contractor" in the Contract Documents in each case shall mean the Contractor who executes each separate Owner–Contractor Agreement.
6.1.3 The Owner shall provide for coordination of the activities of the Owner's own forces and of each separate contractor with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with other separate contractors and the Owner in reviewing their construction schedules when directed to do so. The Contractor shall make any revisions to the construction schedule and Contract Sum deemed necessary after a joint review and mutual agreement. The construction schedules shall then constitute the schedules to be used by the Contractor, separate contractors and the Owner until subsequently revised.
6.1.4 Unless otherwise provided in the Contract Documents, when the Owner performs construction or operations related to the Project with the Owner's own forces, the Owner shall be deemed to be subject to the same obligations and to have the same rights which apply to the Contractor under the Conditions of the Contract, including, without excluding others, those stated in Article 3, this Article 6 and Articles, 10, 11 and 12.
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 12.1 The term “
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 1.1.4, 6 Construction Change Directive, Definition of
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 10.1 Contractor reserves the right to be the only General Contractor on the project and will not relinquish the General Contractor position to another party unless this Agreement is terminated pursuant to Article 24, or unless the parties otherwise agree in an executed Change Order. Persons not contracted directly with the Contractor will not be allowed on the Project Site unless the Owner has authorized access to the Work site and Contractor approves their requested access dates and times, which approval shall not be unreasonably withheld.
10.2 Contractor shall not be responsible for any damage, delay, or increased Cost of Work associated with any acts or omissions of any separate Contractor employed by Owner.
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 12.1 The term "Separate Contractor(s)" shall mean other contractors retained by the Owner under separate agreements. The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and with Separate Contractors retained under Conditions of the Contract substantially similar to those of this Contract, including those provisions of the Conditions of the Contract related to insurance and waiver of subrogation.
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. 6.1 OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS
6.1.1 Strike “and waiver of subrogation” from the end of the second sentence.
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. A. Duty of Cooperation with Owner s’ Separate Contractors.
1. Defects which may develop in the Separate Contractors ’construction or operations after the performance of the Work; or
2. Defects in the Separate Contractors ’ construction or operations of which Design- Build Firm gives Owner notice immediately upon discovery and without then proceeding with the Work affected. If Design-Build Firm or others engaged by or under the control of Design-Build Firm cause(s) physical damage to the construction or property of any Separate Contractor, the Design-Build Firm, upon notice from Owner, shall remedy such damage at its sole expense. If a dispute arises between Design-Build Firm and any Separate Contractor as to each other s’ responsibility for cleaning up, Owner may clean up and charge the cost to Design-Build Firm or the Separate Contractor as Owner shall determine to be just.
CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS. A.6.1 OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTR
6.1.1 The Owner reserves the right to perform construction or operations related to the P S