Delays to the Work. 8.2.1 If Design-Builder is delayed in the performance of the Work due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own, Subcontractors, Design Consultants, or those for whom Design-Builder, Subcontractors, or Design Consultants are responsible, Design-Builder may submit a request for a Work Order that the Contract Time(s) for performance be reasonably extended by Work Order. By way of example, events that Department may consider for an extension of the Contract Time(s) include acts or omissions of Department or anyone under Department’s control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Materials, wars, floods in excess of the base flood (as defined in the Division 1 Amendment), hurricane force winds,
8.2.2 In addition to Design-Builder’s right to a time extension for those events set forth in Section 8.2.1 above, Design-Builder shall also be entitled to submit a request of a Work Order for an appropriate adjustment of the Contract Price provided, however, that the Contract Price shall not be adjusted for those events set forth in Section 8.2.1 above that are beyond the control of both Design-Builder and Department, including the events of wars, floods in excess of the base flood (as defined in the Division 1 Amendment), hurricane force wind, tornados, labor disputes, and earthquakes that cause ground accelerations in excess of AASHTO bridge design standards for the Site.
8.2.3 As a condition precedent to Design-Builder receiving an extension of the Contract Time(s), Design-Builder shall demonstrate that: (i) notice has been given by Design-Builder as provided in these General Conditions; (ii) the delay impacts the critical path (as reflected on the most recent monthly Baseline Schedule update) and is outside the reasonable control of Design- Builder; (iii) Design-Builder’s performance would not have been concurrently delayed or interrupted by any event other than those identified in Section 8.2.1 above; (iv) Design-Builder, in view of all the circumstances, has exercised reasonable efforts to avoid the delay and did not cause the delay; and (v) Design-Builder has complied with the requirements of Section 8.3 below. Delays of Subcontractors shall be deemed to be within the reasonable control of Design- Builder, unless such delays are themselves excusable in accordance with the provisions of Section 8.2.1 above.
8.2.4 Should Department have a reasonabl...
Delays to the Work. 5.4.1 Notwithstanding any other provision to the contrary, any delay and resulting damages that arise out of, or relate to, problems caused by Owner or for which Owner is responsible shall be resolved pursuant to Section 13.3 hereof.
5.4.2 If the Project is delayed due to the Design-Build Subcontractor or anyone for whom Design-Build Subcontractor is responsible, and not due to Design-Builder or Owner, Design-Build Subcontractor shall compensate and indemnify Design-Builder for all costs, damages, and expenses arising from such delay, including but not limited to any liquidated damages or other damages that Owner may assess against Design-Builder which are attributable to Design-Build Subcontractor or anyone for whom Design-Build Subcontractor is responsible. In addition, Design-Build Subcontractor shall, at the direction of Design-Builder and at Design-Build Subcontractor’s own cost and expense, work such overtime and take such other measures as may be necessary to make up for all time lost in the completion of the Project due to such delay.
Delays to the Work. 8.2.1 If Design-Builder is delayed in the performance of the Work due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own or those for whom Design-Builder is responsible, the Contract Time(s) for performance shall be reasonably extended by Change Order. By way of example, events that will entitle Design-Builder to an extension of the Contract Time(s) include acts or omissions of Owner or anyone under Owner's control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Conditions, wars, floods, labor disputes, unusual delay in transportation, epidemics abroad, earthquakes, adverse weather conditions not reasonably anticipated, and other acts of God.
Delays to the Work. 8.2.1 If Design-Builder is delayed in the performance of the Work due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own or those for whom Design-Builder is responsible, the Contract Time(s) for performance shall be reasonably extended by Change Order. By way of example, events that will entitle Design-Builder to an extension of the Contract Time(s) include acts or omissions of Owner or anyone under Owner's control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Conditions, wars, floods, labor disputes, unusual delay in transportation, epidemics abroad, earthquakes, adverse weather conditions not reasonably anticipated, and other acts of God.
8.2.2 In addition to Design-Builder's right to a time extension for those events set forth in Section 8.2.1 above, Design-Builder shall also be entitled to an appropriate adjustment of the Contract Price provided, however, that the Contract Price shall not be adjusted for those events set forth in Section 8.2.1 above that are beyond the control of both Design-Builder and Owner, including the events of war, floods, labor disputes, earthquakes, epidemics, adverse weather conditions not reasonably anticipated, and other acts of God.
Delays to the Work. 6.2.1 If Design-Builder is delayed in the performance of the Work due to Uncontrollable Circumstances, the Contract Time(s) for performance shall be reasonably extended by Change Order, and the Schedule adjusted accordingly.
6.2.2 In addition to Design-Builder’s right to a time extension for delays in the Work under GC 6.2.1, Design-Builder shall also be entitled to an equitable adjustment of the Contract Price and equitable commutation of any Liquidated Damages under Section 5.4 of the Agreement. GC 7.0 Changes to the Contract Price and Time
Delays to the Work. 8.2.1 If Design-Builder is delayed in the performance of the Work due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own or those for whom Design-Builder is responsible, the Contract Time(s) for performance shall be reasonably extended by Change Order. By way of example, events that will entitle Design-Builder to an extension of the Contract Time(s) include acts or omissions of Owner or anyone under Owner’s control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Conditions, and Force Majeure Events.
8.2.2 In addition to Design-Builder’s right to a time extension for those events set forth in Section 8.2.1 above, Design-Builder shall also be entitled to an appropriate adjustment of the Contract Price provided, however, the Contract Price shall not be adjusted for Force Majeure Events.
Delays to the Work. Within five (5) calendar days of the commencement of a delay caused by circumstances or conditions that are not the fault of and are beyond the control of the Consultant, the Consultant may submit a written request for an extension of Contract Time. MCRC will provide a written response to such request within thirty (30) days after receipt of the Consultant’s request.
a. In the event MCRC determines, in its sole discretion, that an extension of time is warranted because the conditions are not the fault of and are beyond the control of the Consultant, MCRC will issue an amendment equitably adjusting the Contract Time.
b. In the event MCRC determines that an extension of time is not warranted by the circumstances or conditions, MCRC will advise the Consultant in writing of its determination. Such determination by MCRC will be considered final and binding and not subject to further review or consideration.
c. Failure on the part of the Consultant to submit a written request for an extension of Contract Time within the time allowed, shall constitute a complete waiver of the request and extinguish the Consultant’s rights to an extension of Contract Time.
Delays to the Work. 6.0.1 If XXXX is delayed in the performance of the Work that shall cause a change in the date of Substantial Completion due to acts, omissions, conditions, events, or circumstances beyond its control and due to no fault of its own, or, those for whom XXXX is responsible, the Contract Times for performance shall be reasonably extended by Change Order. However, the City and the CM@R must agree on the determination of whether acts, omissions, conditions, events, or circumstances are actually beyond the CM@Rs control and/or whether they are due to no fault of the CM@R, or those for whom XXXX is responsible; if the City and the CM@R do not agree, then an independent third party, selected by both parties, shall make the determination of whether acts, omissions, conditions, events, or circumstances are actually beyond the CM@Rs control and/or whether they are due to no fault of the CM@R, or those for whom XXXX is responsible.
6.0.2 XXXX shall request an increase in the Contract Time by written notice including an estimate of probable effect of delay on progress of the Work within three (3) days of the occurrence of the delay. In the case of a continuing delay only one request is necessary.
6.0.3 By way of example, events that shall entitle XXXX to an extension of the Contract Time include acts or omissions of City or anyone under City’s control (including separate Contractors), changes in the Work, Differing Site Conditions, Hazardous Conditions, delays by regulating agencies, wars, floods, labor disputes, unusual delay in transportation, epidemics abroad, earthquakes, adverse weather conditions not reasonably anticipated, and other acts of God.
6.0.4 If adverse weather conditions are the basis for a request for additional Contract Time, such requests shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled Substantial Completion. All terms, conditions and definitions necessary for the application of this paragraph shall be as set forth on the City of Flagstaff’s Table of “Monthly Anticipated Adverse Weather Calendar Days” and the explanatory paragraphs attached thereto.
6.0.5 It is understood, however, that permitting XXXX to proceed to complete any Work, or any part of the Work, after the date to which the time of completion may have been extended, shall in no way act as a waiver on the part of the Cit...
Delays to the Work. 6.1. If work is delayed or interrupted due to the fault of the Employer then the Contractor will be entitled to be paid for any direct losses incurred.
6.2. The Employer must ensure that the working area is occupied exclusively by the contractor as other trades working in the same area may cause chargeable delays.
6.3. All agreed preparation works must be complete and to a satisfactory standard in readiness for us to start the agreed tasks. Failure to do so may cause delay/extra work and may incur extra charges.
Delays to the Work. 8.2.1 If Construction Manager at Risk is delayed in the performance of the Work due to acts, omissions, conditions, events, or circumstances beyond its control are not reasonably anticipated and due to no fault of its own or those for whom Construction Manager at Risk is responsible, the Contract Time(s) for performance shall be reasonably extended by Change Order. By way of example, events that will entitle Construction Manager at Risk to an extension of the Contract Time(s) include acts or omissions of Owner or anyone under Owner’s control (including separate contractors), changes in the Work, Differing Site Conditions, Hazardous Materials (that were not created by the CMR Parties or that were known by or in the exercise of reasonable care should have been known by the CMR Parties at the time the GMP Proposal is agreed upon), wars, floods, labor disputes (other than by employees of the CMR Parties), unusual delay in transportation, epidemics abroad, earthquakes, adverse weather conditions not reasonably anticipated, and other acts of God.