Determination of Final Completion. When Design/Builder considers the Project finally complete and the Design/Builder is ready for a final inspection, it shall notify the Owner and Owner’s Representative in writing. Thereupon, the Owner’s Representative will perform a final inspection of the Project.
Appears in 5 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Determination of Final Completion. When Design/Builder considers believes that all of the Project Work is finally complete complete, and the Design/Builder is ready for a final inspection, it Design/Builder shall so notify the Owner and Owner’s Representative in writing. Thereupon, the Owner’s Representative Owner will perform a then make final inspection of the ProjectWork and, if the Work is complete in strict accordance with the Contract, and the Contract has been fully performed, then Owner will issue a Certificate for Final Payment, providing for payment of the remainder of the Contract Price, less any amount withheld pursuant to the Contract.
Appears in 4 contracts
Samples: Design and Construction Agreement, Guaranteed Maximum Price Design and Construction Agreement, Design and Construction Agreement
Determination of Final Completion. When Design/Builder considers believes that all of the Project Construction Work is finally complete complete, and the Design/Builder is ready for a final inspection, it Design/Builder shall so notify the Owner and Owner’s Representative Director in writing. Thereupon, The Director (or a designee of the Owner’s Representative ) will perform a then make final inspection of the ProjectConstruction Work and, if the Construction Work is complete in strict accordance with the Contract, and the Contract has been fully performed, then Owner will authorize final payment, providing for payment of the remainder of the Contract Price, less any amount withheld pursuant to the Contract.
Appears in 2 contracts
Samples: Design/Build Contract, Design/Build Contract
Determination of Final Completion. When Design/Builder considers believes that all of the Project Construction Work is finally complete complete, and the Design/Builder is ready for a final inspection, it Design/Builder shall so notify the Owner and Owner’s Representative Director in writing. Thereupon, the The Director (or an independent consultant hired by Owner’s Representative ) will perform a then make final inspection of the ProjectConstruction Work and, if the Construction Work is complete in strict accordance with the Contract, and the Contract has been fully performed, then Owner will issue a Certificate for Final Payment, providing for payment of the remainder of the Contract Price, less any amount withheld pursuant to the Contract.
Appears in 1 contract
Samples: Design/Build Contract
Determination of Final Completion. When Design/Builder the Contractor considers the Project finally complete and the Design/Builder Contractor is ready for a final inspection, it shall notify the Owner and OwnerMunicipality’s Representative in writing. Thereupon, the OwnerMunicipality’s Representative will perform a final inspection of the Project.
Appears in 1 contract
Samples: Design Build Operate Agreement