Final Inspection. If at the Final Inspection the Project Manager determines that all work is completed, the Project Manager shall notify the Contractor in accordance with Section 7.32, PROJECT ACCEPTANCE DATE. Should there be remaining deficiencies which must be corrected the Contractor shall provide an updated Punchlist to the Project Manager, within five (5) days from the Final Inspection Date. The Contractor shall make the necessary corrections. 7.31.2.1 The Project Manager shall confirm the list of deficiencies noted by the Contractor’s punchlist(s) and will notify the Contractor of any other deficiencies that must be corrected before final settlement.