Common use of Final Inspection Clause in Contracts

Final Inspection. If at the Final Inspection the Project Manager determines that all work is completed, the Project Manager shall notify the Contractor in accordance with Section 7.32, PROJECT ACCEPTANCE DATE. Should there be remaining deficiencies which must be corrected the Contractor shall provide an updated Punchlist to the Project Manager, within five (5) days from the Final Inspection Date. The Contractor shall make the necessary corrections. 7.31.2.1 The Project Manager shall confirm the list of deficiencies noted by the Contractor’s punchlist(s) and will notify the Contractor of any other deficiencies that must be corrected before final settlement.

Appears in 18 contracts

Samples: Contract for Goods or Services, Contract for Goods or Services, Contract for Goods or Services

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!