Common use of FOB NINETY DAY SCHEDULE Clause in Contracts

FOB NINETY DAY SCHEDULE. No later than the twenty-fifth (25th) Day of each Month, Project Co shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the "FOB Ninety Day Schedule"). The FOB Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the FOB Delivery Window, LNG Tanker and FOB SCQ and Production Facility for each cargo and, to the extent applicable, designation of relevant cargoes as “Diverted Cargoes”. In the absence of agreement between the Parties otherwise, the FOB Ninety Day Schedule shall maintain the FOB SCQ and FOB Delivery Windows as identified in the FOB ADP. THIS PORT LIABILITY AGREEMENT (this “Agreement”) is effective as of _______, 20__, and is made by and between [Corpus Christi] a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] (“Terminal Owner”), and [INSERT NAME(S) OF VESSEL OWNER(S), a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] ([collectively] “Vessel Owner”).

Appears in 3 contracts

Samples: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC), Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC), Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)

AutoNDA by SimpleDocs

FOB NINETY DAY SCHEDULE. No later than the twenty-fifth (25th) Day of each Month, Project Co shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the "FOB Ninety Day Schedule"). The FOB Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the FOB Delivery Window, LNG Tanker and FOB SCQ and Production Facility for each cargo and, to the extent applicable, designation of relevant cargoes as “Diverted Cargoes”. In the absence of agreement between the Parties otherwise, the FOB Ninety Day Schedule shall maintain the FOB SCQ and FOB Delivery Windows as identified in the FOB ADP. 121 THIS PORT LIABILITY AGREEMENT (this “Agreement”) is effective as of _______, 20__, and is made by and between [Corpus Christi] a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] (“Terminal Owner”), and [INSERT NAME(S) OF VESSEL OWNER(S), a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] ([collectively] “Vessel Owner”).

Appears in 1 contract

Samples: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)

FOB NINETY DAY SCHEDULE. No later than the twenty-fifth (25th) Day of each Month, Project Co shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the "FOB Ninety Day Schedule"). The FOB Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the FOB Delivery Window, LNG Tanker and FOB SCQ and Production Facility for each cargo and, to the extent applicable, designation of relevant cargoes as “Diverted Cargoes”. In the absence of agreement between the Parties otherwise, the FOB Ninety Day Schedule shall maintain the FOB SCQ and FOB Delivery Windows as identified in the FOB ADP. 102 THIS PORT LIABILITY AGREEMENT (this “Agreement”) is effective as of _______, 20__, and is made by and between [Corpus Christi] a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] (“Terminal Owner”), and [INSERT NAME(S) OF VESSEL OWNER(S), a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] ([collectively] “Vessel Owner”).

Appears in 1 contract

Samples: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)

AutoNDA by SimpleDocs

FOB NINETY DAY SCHEDULE. No later than the twenty-fifth (25th) Day of each Month, Project Co shall issue a forward plan of deliveries for the three (3)-Month period commencing on the first Day of the following Month thereafter (e.g., the Ninety Day Schedule for the three (3)-Month period commencing on May 1st shall be issued no later than the twenty-fifth (25th) Day of April) (such plan, as amended from time to time in accordance with procedures set forth in this Agreement, the "FOB Ninety Day Schedule"). The FOB Ninety Day Schedule shall set forth by cargo the forecast pattern of deliveries, including the FOB Delivery Window, LNG Tanker and FOB SCQ and Production Facility for each cargo and, to the extent applicable, designation of relevant cargoes as “Diverted Cargoes”. In the absence of agreement between the Parties otherwise, the FOB Ninety Day Schedule shall maintain the FOB SCQ and FOB Delivery Windows as identified in the FOB ADP. THIS PORT LIABILITY AGREEMENT (this “Agreement”) is effective as of _______, 20__, and is made by and between [Corpus Christi] a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] (“Terminal Owner”), and [INSERT NAME(S) OF VESSEL OWNER(S), a [TYPE OF ENTITY AND JURISDICTION OF ORGANIZATION] ([collectively] “Vessel Owner”).

Appears in 1 contract

Samples: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)