Material Breach. 27.1 In the event of a material breach by the Contractor the Authority may either: 27.1.1 take over the provision of some or all of the Goods or Services; or 27.1.2 partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or 27.1.3 terminate the whole of the Contract. 27.2 If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days. 27.3 In the event that the Contractor fails to comply with clause 27.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 35 contracts
Samples: Contract for the Provision of Building Services, Agreement, Contract for the Provision of Building Services
Material Breach. 27.1 26.1. In the event of a material breach by the Contractor the Authority may either:
27.1.1 26.1.1. take over the provision of some or all of the Goods or Services; or
27.1.2 26.1.2. partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 26.1.3. terminate the whole of the Contract.
27.2 26.2. If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 26.3. In the event that the Contractor fails to comply with clause 27.2 26.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 19 contracts
Samples: Professional Services, Visitor Centre Service Agreement, Services Contract
Material Breach. 27.1 In the event of a material breach by the Contractor the Authority may either:
27.1.1 take : take over the provision of some or all of the Goods or Services; or
27.1.2 or partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 or terminate the whole of the Contract.
27.2 If . If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 . In the event that the Contractor fails to comply with clause 27.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 10 contracts
Samples: Commercial Agreement, Supply of Veterinary Services Agreement, Purchase Agreement
Material Breach. 27.1 In the event of a material breach by the Contractor the Authority may either:
27.1.1 take Take over the provision of some or all of the Goods or Services; or
27.1.2 partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 terminate Terminate the whole of the Contract.
27.2 If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 In the event that the Contractor fails to comply with clause 27.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 7 contracts
Samples: Taxi Services Agreement, Taxi Services Agreement, Taxi Services Agreement
Material Breach. 27.1 26.1. In the event of a material breach by the Contractor the Authority may either:
27.1.1 26.1.1. take over the provision of some or all of the Goods or Services; or
27.1.2 26.1.2. partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 26.1.3. terminate the whole of the Contract.
27.2 26.2. If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 26.3. In the event that the Contractor fails to comply with clause 27.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 5 contracts
Samples: Facilities Management Agreement, Facilities Management Agreement, Contract for the European Social Fund
Material Breach. 27.1 26.1 In the event of a material breach by the Contractor the Authority may either:
27.1.1 26.1.1 take over the provision of some or all of the Goods or Services; or
27.1.2 26.1.2 partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 26.1.3 terminate the whole of the Contract.
27.2 26.2 If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 26.3 In the event that the Contractor fails to comply with clause 27.2 26.2 above the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 1 contract
Samples: Contract for Refurbishment and Supply & Installation of Dental Chair
Material Breach. 27.1 26.1. In the event of a material breach by the Contractor the Authority may either:
27.1.1 26.1.1. take over the provision of some or all of the Goods or Services; or
27.1.2 26.1.2. partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 26.1.3. terminate the whole of the Contract.
27.2 26.2. If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten thirty (1030) Working Days.
27.3 26.3. In the event that the Contractor fails to comply with clause 27.2 26.2 the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.
Appears in 1 contract
Samples: Provision of Legacy Custodial Locking Parts and Components
Material Breach. 27.1 In the event of a material breach by the Contractor the Authority may either:
27.1.1 take over the provision of some or all of the Goods or Services; or
27.1.2 partially terminate the Contract, reduce the Contract Price, and provide or procure a third party to provide that part of the Goods or Services at the Contractor’s cost; or
27.1.3 terminate the whole of the Contract.
27.2 If the Contractor fails to supply any of the Goods or Services in accordance with the Contract, and the failure is remediable, the Contractor shall, on the instruction of the Authority, at its own cost remedy the failure (and any damage resulting from the failure) within ten (10) Working Days.
27.3 In the event that the Contractor fails to comply with clause 27.2 above the Authority may terminate the Contract (or that part of the Contract) with immediate effect by notice in writing.