Common use of Minimisation of Impact Clause in Contracts

Minimisation of Impact. Upon receiving a notice under clause 20.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 18 contracts

Samples: Storage and Handling Agreement, Storage and Handling Agreement, Storage and Handling Agreement

AutoNDA by SimpleDocs

Minimisation of Impact. Upon receiving a notice under clause 20.3 15.4 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 14 contracts

Samples: Storage & Handling Agreement, Port Terminal Services Agreement, Port Terminal Services Agreement

Minimisation of Impact. Upon receiving a notice under clause 20.3 15.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 7 contracts

Samples: Storage & Handling Agreement, Port Terminal Services Agreement, Port Terminal Services Agreement

Minimisation of Impact. Upon upon receiving a notice under clause 20.3 28.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations Obligation or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 3 contracts

Samples: Storage & Handling Agreement, Storage & Handling Agreement, Storage & Handling Agreement

Minimisation of Impact. Upon upon receiving a notice under clause 20.3 27.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations Obligation or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement Agreement, or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) ), are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 2 contracts

Samples: Storage & Handling Agreement, Storage & Handling Agreement

Minimisation of Impact. Upon upon receiving a notice under clause 20.3 27.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations Obligation or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 2 contracts

Samples: Storage & Handling Agreement, Storage & Handling Agreement

Minimisation of Impact. 16.4.1 Upon receiving a notice under clause 20.3 16.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement Contract or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 1 contract

Samples: Supply Agreement

AutoNDA by SimpleDocs

Minimisation of Impact. 14.4.1 Upon receiving a notice under clause 20.3 14.3 the Parties will meet to discuss and agree: (a) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) what modifications or additions to the terms of this Agreement Contract or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 1 contract

Samples: Supply Agreement

Minimisation of Impact. Upon receiving a notice under clause 20.3 13.3, the Parties will meet to discuss and agree: (ab) what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (bc) whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (cd) what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 1 contract

Samples: Packing & Processing Agreement

Minimisation of Impact. Upon receiving a notice under clause 20.3 13.3, the Parties will meet to discuss and agree: (a) : what action can be taken to minimise the effect of the Force Majeure Event on the performance by the Affected Party of the Affected Obligation; (b) ; whether the Affected Party is able to work around the Force Majeure Event either to prevent the delay in the performance of the Affected Obligations or to minimise the impact of that delay; and (c) and what modifications or additions to the terms of this Agreement or any other agreements between the Parties (including without limitation any modifications or additions relating to the appointment of any additional costs) are required to give effect to any proposal to minimise the effect of the Force Majeure Event.

Appears in 1 contract

Samples: Packing & Processing Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!