Monthly or Progress Payments. A. The City Council of the City of Northglenn has appropriated the money necessary to fund this project. The Owner shall pay the Trade Contractor in current funds for the performance of the work, subject to any additions and deletions, by written change order, the total sum not to exceed dollars ($ ) (the “Original Contract Amount”). Notwithstanding anything to the contrary contained in this Agreement, no change order or other form of directive by the Owner requiring additional compensable work to be performed, which causes the aggregate amount payable under this Agreement, to exceed the amount appropriated for the Original Contract Amount, unless the Trade Contractor is given written assurance by the City of Northglenn that lawful appropriations have been made by the City Council of the City of Northglenn to cover the cost of the additional work. B. The Engineer has, by separate agreement with the Owner, agreed to include in its monthly work estimate to the Owner, a review of the Trade Contractor’s estimates of the value of all work, labor, and materials of the Trade Contractor incorporated into the Project. The Trade Contractor hereby agrees that estimates provided to the Engineer for review for the Owner shall be for work actually performed upon the project and that all such work, including labor and materials, have been paid. The determination of the amount of work completed on each application for payment by the Trade Contractor shall be made by the Engineer and shall thereafter be subject to approval by the Owner. Such determination, however, by the Engineer or approval by the Owner shall not be construed as acceptance of the work. 1. Before the first application for payment, the Trade Contractor shall submit to the Engineer and Owner a schedule of values to be allocated to the various portions of the Work, which in the aggregate equals the total Contract Sum, divided so as to facilitate payments to subcontractors, supported by such evidence of correctness as the Engineer may direct. This schedule, when approved by the Engineer, shall be used to monitor the progress of the Work and as a basis for making progress payments hereunder. Application for monthly progress payments shall be made in writing in accordance with this Contract and shall be submitted on approved forms provided by the Owner and shall be submitted to the Owner on or before the twentieth (20th) day of each month. Applications received on time will be paid on the twentieth (20th) day of the following month, providing that the Owner approves such recommendations of the Engineer. Applications received after the twentieth (20th) day of each month shall paid after the Owner’s next pay period.
Appears in 3 contracts
Samples: Trade Contractor Agreement, Trade Contractor Agreement, Trade Contractor Agreement
Monthly or Progress Payments. A. The City Council of the City of Northglenn NURA Board has appropriated the money necessary to fund this project. The Owner XXXX shall pay the Trade Contractor in current funds for the performance of the work, subject to any additions and deletions, by written change order, the total sum not to exceed dollars Four Hundred Sixty-two Thousand Five Hundred Eighty-five Dollars and Zero Cents ($ $462,585.00) (the “Original Contract Amount”). Notwithstanding anything to the contrary contained in this Agreement, no change order or other form of directive by the Owner XXXX requiring additional compensable work to be performed, which causes the aggregate amount payable under this Agreement, to exceed the amount appropriated for the Original Contract Amount, unless the Trade Contractor is given written assurance by the City of Northglenn NURA that lawful appropriations have been made by the City Council of the City of Northglenn NURA Board to cover the cost of the additional work.
B. The Engineer has, by separate agreement with the OwnerXXXX, agreed to include in its monthly work estimate to the OwnerNURA, a review of the Trade Contractor’s estimates of the value of all work, labor, and materials of the Trade Contractor incorporated into the Project. The Trade Contractor hereby agrees that estimates provided to the Engineer for review for the Owner NURA shall be for work actually performed upon the project and that all such work, including labor and materials, have been paid. The determination of the amount of work completed on each application for payment by the Trade Contractor shall be made by the Engineer and shall thereafter be subject to approval by the OwnerXXXX. Such determination, however, by the Engineer or approval by the Owner NURA shall not be construed as acceptance of the work.
1. Before the first application for payment, the Trade Contractor shall submit to the Engineer and Owner NURA a schedule of values to be allocated to the various portions of the Work, which in the aggregate equals the total Contract Sum, divided so as to facilitate payments to subcontractors, supported by such evidence of correctness as the Engineer may direct. This schedule, when approved by the Engineer, shall be used to monitor the progress of the Work and as a basis for making progress payments hereunder. Application for monthly progress payments shall be made in writing in accordance with this Contract and shall be submitted on approved forms provided by the Owner NURA and shall be submitted to the Owner NURA on or before the twentieth (20th) day of each month. Applications received on time will be paid on the twentieth (20th) day of the following month, providing that the Owner NURA approves such recommendations of the Engineer. Applications received after the twentieth (20th) day of each month shall paid after the OwnerXXXX’s next pay period.
Appears in 1 contract
Samples: Trade Contractor Agreement