Monthly Progress Schedule. 13 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 14 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 15 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 16 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 17 dates for activities planned in the next update period. The Monthly Progress Schedule must 18 include the following:
Appears in 3 contracts
Samples: Design Build Maintain Agreement, Design Build Maintain Agreement, Design Build Maintain Agreement
Monthly Progress Schedule. 13 42 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 14 43 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 15 44 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 16 1 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 17 2 dates for activities planned in the next update period. The Monthly Progress Schedule must 18 3 include the following:
Appears in 3 contracts
Samples: Design Build Maintain Agreement, Design Build Maintain Agreement, Design Build Maintain Agreement