Common use of Owner’s Response Clause in Contracts

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The Owner will not grant time extensions for delays that do not affect the Contract Completion Date. 9.9.4.2 The Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to a time extension in the amount requested.

Appears in 42 contracts

Samples: Design Build Contract, Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The .1 Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Datedate. 9.9.4.2 The .2 Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to a time extension in the amount requested.

Appears in 29 contracts

Samples: Contract for Construction, Contract for Construction, Construction Contract

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Datedate. 9.9.4.2 The Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to Contractor’s request for a time extension in the amount requestedshall be deemed rejected by Owner.

Appears in 21 contracts

Samples: Construction Services Agreement, Construction Services Agreement, Construction Manager at Risk Agreement

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Date. 9.9.4.2 The Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to Contractor’s request for a time extension in the amount requestedshall be deemed rejected by Owner.

Appears in 8 contracts

Samples: Construction Contract, Construction Management Agreement, Construction Management Agreement

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Datedate. 9.9.4.2 The Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to a time extension in the amount requestedrequested Contractor’s request for a time extension shall be deemed rejected by Owner.

Appears in 6 contracts

Samples: Design/Build Agreement, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Datedate. 9.9.4.2 The Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to a time extension in the amount requested.

Appears in 6 contracts

Samples: General Construction Services Contract, General Construction Services Contract, Construction Manager at Risk Contract

Owner’s Response. The Owner will respond to the Time Extension Request by providing to the Contractor written notice of the number of days granted, if any, and giving its reason if this number differs from the number of days requested by the Contractor. 9.9.4.1 The 8.9.4.1 Owner will not grant time extensions for delays that do not affect the Contract Substantial Completion Datedate. 9.9.4.2 The 8.9.4.2 Owner will respond to each properly submitted Time Extension Request within fifteen (15) calendar days following receipt. If the Owner cannot reasonably make a determination about the Contractor’s entitlement to a time extension within that time, the Owner will notify the Contractor in writing. Unless otherwise agreed by the Contractor, the Owner has no more than fifteen (15) additional calendar days to prepare a final response. If the Owner fails to respond within forty-five (45) calendar days from the date the Time Extension Request is received, the Contractor is entitled to Contractor’s request for a time extension in the amount requestedshall be deemed rejected by Owner.

Appears in 1 contract

Samples: Standard Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!