Possible Price and Time Adjustments. Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if: 1. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to City with respect to Contract Price and Contract Time by the submission of a Bid or becoming bound under a negotiated contract; or 2. the existence of such condition could reasonably have been discovered or revealed as a result of the examination of the Contract Documents or the Site; or 3. Contractor failed to give the written notice as required by Paragraph 4.03.A.

Appears in 7 contracts

Samples: Construction Contract, Construction Contract, Construction Contract