Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract. b. Where the Contractor enters into a subcontract, they shall cause a term to be included in such subcontract: (1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion; (2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed; (3) providing that where the Contractor fails to comply with clause 39.b.(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b.
Appears in 5 contracts
Samples: Contract for SFJHQ Deployable Acoustic Rooms, Provision of Typhoon Mids Bu2 Servicing Support, Contract
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s 's obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontract, they Subcontract he shall cause a term to be included in such subcontractSubcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(139.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b39.b(2) after a reasonable time has passed; and
(4) requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as clauses 39.b(1) to 39.b(4).
Appears in 4 contracts
Samples: Contract, Intelligent Ship Phase 3 Contract, Contract
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s 's obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontractSubcontract, they he shall cause a term to be included in such subcontractSubcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(1Clause 14.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.bClause 14.b(2) after a reasonable time has passed; and
(4) requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as Clauses 14.b(1) to 14.b(4).
Appears in 3 contracts
Samples: Purchase Agreement, Purchase Agreement, Purchase Agreement
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontract, they Subcontract he shall cause a term to be included in such subcontractSubcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(139.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b39.b(2) after a reasonable time has passed; and
(4) requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as clauses 39.b(1) to 39.b(4).
Appears in 3 contracts
Samples: Provision of a Mission Aircrew Isr Operator Training, Supply Agreement, Supply Agreement
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontract, they shall cause a term to be included in such subcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b.
Appears in 1 contract
Samples: Contract
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontractSubcontract, they he shall cause a term to be included in such subcontractSubcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(139.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b39.b(2) after a reasonable time has passed; and
(4) requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as clauses 39.b(1) to 39.b(4).
Appears in 1 contract
Samples: Contract
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract.
b. . Where the Contractor enters into a subcontract, they Subcontract he shall cause a term to be included in such subcontract:
(1) Subcontract: providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) ; providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) ; providing that where the Contractor fails to comply with clause 39.b.(139.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.b.39.b(2) after a reasonable time has passed; and requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as clauses 39.b(1) to 39.b(4). Termination
Appears in 1 contract
Samples: Provision of Information Management & Information Technology (Imit) Training Framework
Subcontracting and Prompt Payment. a. Subcontracting any part of the Contract shall not relieve the Contractor of any of the Contractor’s obligations, duties or liabilities under the Contract.
b. Where the Contractor enters into a subcontract, they Subcontract he shall cause a term to be included in such subcontractSubcontract:
(1) providing that where the Subcontractor submits an invoice to the Contractor, the Contractor will consider and verify that invoice in a timely fashion;
(2) providing that the Contractor shall pay the Subcontractor any sums due under such an invoice no later than a period of thirty (30) days from the date on which the Contractor has determined that the invoice is valid and undisputed;
(3) providing that where the Contractor fails to comply with clause 39.b.(1Clause 15.b(1) above, and there is an undue delay in considering and verifying the invoice, that the invoice shall be regarded as valid and undisputed for the purposes of clause 39.bClause 15.b(2) after a reasonable time has passed; and
(4) requiring the counterparty to that Subcontract to include in any Subcontract which it awards, provisions having the same effect as Clauses 15.b(1) to 15.b(4).