UDC Responsibilities. Recognizing the ISO’s duty to ensure efficient use and reliable operation of the ISO Controlled Grid consistent with the Applicable Reliability Criteria, each UDC shall: 4.3.1 operate and maintain its facilities, in accordance with applicable safety and reliability standards, regulatory requirements, applicable operating guidelines, applicable rates, tariffs, statutes and regulations governing their provision of service to their End- Use Customers and Good Utility Practice so as to avoid any material adverse impact on the ISO Controlled Grid; 4.3.2 provide the ISO Outage Coordination Office each year with a schedule of upcoming maintenance that has a reasonable potential of impacting the ISO Controlled Grid in accordance with Section 2.3.3.5 of this ISO Tariff; and 4.3.3 coordinate with the ISO, Participating TOs and Generators to ensure that ISO Controlled Grid Critical Protective Systems, including relay systems, are installed and maintained in order to function on a coordinated and complementary basis with UDCs, Generator’s and Participating TO’s protective systems.
Appears in 3 contracts
Samples: Transmission Control Agreement, Transmission Control Agreement, Transmission Control Agreement
UDC Responsibilities. Recognizing the ISO’s duty to ensure efficient use and reliable operation of the ISO Controlled Grid consistent with the Applicable Reliability Criteria, each UDC shall:
4.3.1 operate and maintain its facilities, in accordance with applicable safety and reliability standards, regulatory requirements, applicable operating guidelines, applicable rates, tariffs, statutes and regulations governing their provision of service to their End- End-Use Customers and Good Utility Practice so as to avoid any material adverse impact on the ISO Controlled Grid;
4.3.2 provide the ISO Outage Coordination Office each year with a schedule of upcoming maintenance that has a reasonable potential of impacting the ISO Controlled Grid in accordance with Section 2.3.3.5 of this ISO Tariff; and
4.3.3 coordinate with the ISO, Participating TOs and Generators to ensure that ISO Controlled Grid Critical Protective Systems, including relay systems, are installed and maintained in order to function on a coordinated and complementary basis with UDCsUDC’s, Generator’s and Participating TO’s protective systems.
Appears in 1 contract
Samples: Transmission Control Agreement
UDC Responsibilities. Recognizing the ISO’s 's duty to ensure efficient use and reliable operation of the ISO Controlled Grid consistent with the Applicable Reliability Criteria, each UDC shall:
4.3.1 operate and maintain its facilities, in accordance with applicable safety and reliability standards, regulatory requirements, applicable operating guidelines, applicable rates, tariffs, statutes and regulations governing their provision of service to their End- End-Use Customers and Good Utility Practice so as to avoid any material adverse impact on the ISO Controlled Grid;¡
4.3.2 provide the ISO Outage Coordination Office each year with a schedule of upcoming maintenance that has a reasonable potential of impacting the ISO Controlled Grid in accordance with Section 2.3.3.5 of this ISO Tariff; ¡ and
4.3.3 coordinate with the ISO, Participating TOs and Generators to ensure that ISO Controlled Grid Critical Protective Systems, including relay systems, are installed and maintained in order to function on a coordinated and complementary basis with UDCs, Generator’s 's and Participating TO’s 's protective systems.
Appears in 1 contract
Samples: Transmission Control Agreement
UDC Responsibilities. Recognizing the ISO’s duty to ensure efficient use and reliable operation of the ISO Controlled Grid consistent with the Applicable Reliability Criteria, each UDC shall:
4.3.1 operate and maintain its facilities, in accordance with applicable safety and reliability standards, regulatory requirements, applicable operating guidelines, applicable rates, tariffs, statutes and regulations governing their provision of service to their End- End-Use Customers and Good Utility Practice so as to avoid any material adverse impact on the ISO Controlled Grid;
4.3.2 provide the ISO Outage Coordination Office each year with a schedule of upcoming maintenance that has a reasonable potential of impacting the ISO Controlled Grid in accordance with Section 2.3.3.5 of this ISO Tariff; and
4.3.3 coordinate with the ISO, Participating TOs and Generators to ensure that ISO Controlled Grid Critical Protective Systems, including relay systems, are installed and maintained in order to function on a coordinated and complementary basis with UDCs, Generator’s and Participating TO’s protective systems.
Appears in 1 contract
Samples: Transmission Control Agreement
UDC Responsibilities. Recognizing the ISO’s duty to ensure efficient use and reliable operation of the ISO Controlled Grid consistent with the Applicable Reliability Criteria, each UDC shall:
4.3.1 4. 3.1 operate and maintain its facilities, in accordance with applicable safety and reliability standards, regulatory requirements, applicable operating guidelines, applicable rates, tariffs, statutes and regulations governing their provision of service to their End- End-Use Customers and Good Utility Practice so as to avoid any material adverse impact on the ISO Controlled Grid;
4.3.2 4. 3.2 provide the ISO Outage Coordination Office each year with a schedule of upcoming maintenance that has a reasonable potential of impacting the ISO Controlled Grid in accordance with Section 2.3.3.5 of this ISO Tariff; and
4.3.3 4. 3.3 coordinate with the ISO, Participating TOs and Generators to ensure that ISO Controlled Grid Critical Protective Systems, including relay systems, are installed and maintained in order to function on a coordinated and complementary basis with UDCsUDC’s, Generator’s and Participating TO’s protective systems.
Appears in 1 contract
Samples: Transmission Control Agreement