When Delay Claim Deemed Waived. Any claim to extend the Contract Time and Material Completion and Occupancy Date not made in writing to Owner within the above time periods shall be deemed waived and shall not thereafter be valid. In the case of a continuing delay as a result of a single event, only one claim submission is necessary.
Appears in 74 contracts
Samples: Construction Contract, Design Build Contract, Design Build Contract
When Delay Claim Deemed Waived. Any claim to extend the Contract Time and Sum or Material Completion and Occupancy Date not made in writing to Owner within the above time periods shall be deemed waived and shall not thereafter be valid. In the case of a continuing delay as a result of a single event, only one claim submission is necessary.
Appears in 35 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
When Delay Claim Deemed Waived. Any claim to extend the Contract Time and Material Substantial Completion and Occupancy Date not made in writing to Owner Board within the above time periods shall be deemed waived and shall not thereafter be valid. In the case of a continuing delay as a result of a single event, only one claim submission is necessary.
Appears in 3 contracts
Samples: Construction Management at Risk Agreement, Construction Management at Risk Agreement, Construction Management at Risk Agreement
When Delay Claim Deemed Waived. Any claim to extend the Contract Time and Material Completion and Occupancy Date not made in writing to Owner within the above time periods shall be deemed waived and shall not thereafter be valid. In the case of a continuing delay as a result of a single event, only one claim submission is necessary.
Appears in 3 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
When Delay Claim Deemed Waived. Any claim to extend the Contract Time and Sum or Material Completion and Occupancy Date not made in writing to Owner within the above time periods shall be deemed waived and shall not thereafter be valid. In the case of a continuing delay as a result of a single event, only one claim submission is necessary.
Appears in 1 contract