Common use of When Final Completion Required Clause in Contracts

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completion. The Design Professional’s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 4 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completionthe Material Completion Date. The Design Professional’s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 1 contract

Samples: Construction Management Agreement

AutoNDA by SimpleDocs

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completion. The Design Professional’s Professional‟s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 1 contract

Samples: Design Bid Build Construction Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!