Cost and Schedule Proposal definition

Cost and Schedule Proposal means DB Contractor’s proposal furnished to TxDOT pursuant to a Request for Change Proposal in accordance with Section 13.2.1.4 of the Agreement.

Examples of Cost and Schedule Proposal in a sentence

  • Each Cost and Schedule Proposal and Request for Change Order shall (i) be prepared in a form acceptable to TxDOT, (ii) meet all applicable requirements of this Section 10; and (iii) be substantially in the form of Exhibit 12.

  • DB Contractor shall bear the cost of developing the Cost and Schedule Proposal, including any modifications thereto requested by TxDOT, except that costs of design and engineering work required for preparation of plans or exhibits necessary to the Cost and Schedule Proposal, as pre-authorized by TxDOT, may be included in the Change Order as reimbursable items.

  • If TxDOT and Maintenance Contractor agree that a request to increase the Maintenance Price by Maintenance Contractor has merit, but are unable to agree as to the amount of such Maintenance Price increase, TxDOT agrees to mark up the Request for Change Order or Cost and Schedule Proposal, as applicable, provided by Maintenance Contractor to reduce the amount of the Maintenance Price increase as deemed appropriate by TxDOT.

  • This indicates that in case of Telugu, morphological data has rele- vance to sentiment expressed and morphological segmentation would result in loss of such valuable information for sentiment analysis tasks.

  • DB Contractor shall bear the cost of developing the Cost and Schedule Proposal, including any modifications thereto requested by TxDOT, except that costs of design and engineering work required for preparation of plans or exhibits necessary to the Cost and Schedule Proposal, as preauthorized by TxDOT, may be included in the Change Order as reimbursable items.

  • Maintenance Contractor shall bear the cost of developing the Cost and Schedule Proposal, including any modifications thereto requested by TxDOT, except that costs of design and engineering work required for preparation of plans or exhibits necessary to the Cost and Schedule Proposal, as pre- authorized by TxDOT, may be included in the Change Order as reimbursable items.

  • Maintenance Contractor shall prepare a scope of work and cost estimate, and such other information as required by this Section 10.4.2 for each Cost and Schedule Proposal and Request for Change Order.

  • Maintenance Contractor shall bear the cost of developing the Cost and Schedule Proposal, including any modifications thereto requested by TxDOT, except that costs of design and engineering work required for preparation of plans or exhibits necessary to the Cost and Schedule Proposal, as pre-authorized by TxDOT, may be included in the Change Order as reimbursable items.

  • If TxDOT and DB Contractor agree that a request to increase the Maintenance Price by DB Contractor has merit, but are unable to agree as to the amount of such Maintenance Price increase, TxDOT agrees to mark up the Request for Change Order or Cost and Schedule Proposal, as applicable, provided by DB Contractor to reduce the amount of the Maintenance Price increase as deemed appropriate by TxDOT.

  • If TxDOT and DB Contractor agree that a request to increase the Maintenance Price by DB Contractor has merit but are unable to agree as to the amount of such Maintenance Price increase, TxDOT agrees to xxxx up the Request for Change Order or Cost and Schedule Proposal, as applicable, provided by DB Contractor to reduce the amount of the Maintenance Price increase as deemed appropriate by TxDOT.

Related to Cost and Schedule Proposal

  • Project Proposal has the meaning set forth in Section 2.2(b).

  • Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;

  • Annexures means any of the annexures, appendices, supplements or documents annexed to this Agreement and as amended from time to time;

  • Special Contract Attachments means any attachment to this Contract.

  • Technical Proposal means the Contractor’s Technical Proposal dated (Technical Proposal date).

  • TO Technical Proposal means the TO Contractor’s technical response to the CATS+ TORFP dated date of TO Technical Proposal.

  • Superior Acquisition Proposal means a bona fide Acquisition Proposal made by a third party for one or more of the McNeil Partnerships which the general partner of each such McNeil Partnership determines in good faith to be more favorable to the limited partners of such McNeil Partnership from a financial point of view than the Mergers and the other transactions contemplated by this Agreement with respect to such McNeil Partnership, and which such general partner determines in good faith is reasonably likely to be consummated.

  • approved proposal means a proposal approved or deemed to be approved under this Agreement;

  • Acquisition Proposal has the meaning set forth in Section 5.03(a).

  • Day-Ahead Schedule has the meaning set forth in the CAISO Tariff.

  • Indirect cost rate proposal has the same meaning as in 44 Ill. Admin. Code Part 7000.

  • Specification Schedule means the Schedule containing details of the Specification.

  • Material Project Documents means, collectively, the Power Purchase Agreement, the EPC Contract, the Transmission Facilities Construction Agreement, the O&M Agreement, the Coal Supply Agreements, the Coal Transportation Agreement and all other instruments, agreements or other documents arising from or related to the Project, but shall not include any Financing Agreement.

  • Completion Schedule means the fulfilment of the Related Services by the Supplier in accordance with the terms and conditions set forth in the Contract;

  • Responsive Proposal means a Proposal that complies with the material provisions of this RFP.

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Implementation Schedule means the Implementation Schedule in Section VII of the tendering documents.

  • TO Proposal - Technical means the TO Contractor’s technical response to the CATS II TORFP dateddate of TO Proposal – Technical.

  • Superior Proposal has the meaning set forth in Section 5.09(a).

  • RFP Project Documents means the following documents to be entered into in respect of the Project, by the parties to the respective agreements:

  • Notice of Superior Proposal has the meaning set forth in Section 5.09(e).

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • Company Acquisition Proposal means any proposal for a merger or other business combination involving the Company or the acquisition of any equity interest in, or a substantial portion of the assets of, the Company, other than the transactions contemplated by this Agreement.

  • Superior Proposal Notice has the meaning specified in Section 5.4(1)(c).

  • Progress Schedule means a schedule of the Work, in a form satisfactory to Owner, as further set forth in Section 3.02.

  • Annexure F means, if applicable to the Product or the subject matter of this Agreement and read conjunctively with the Contractor’s obligations in terms of the Consumer Protection Act, the express warranties provided by the Contractor in relation to the Product.