Estimated Milestone Schedule definition

Estimated Milestone Schedule shall have the meaning set forth in Section 3.5 of this Agreement.

Examples of Estimated Milestone Schedule in a sentence

  • Neither Party shall be liable for failure to meet the above Estimated Milestone Schedule, any milestone, any in-service date, or any other projected or preliminary schedule in connection with this Agreement, the Work or the ATP.

  • Any Advance Notice given by the Proposing Party to the Recipientshall include a good faith estimate of the impact of the Material Change on the Estimated Milestone Schedule and an explanation of why such Material Change is being proposed.

  • Any Advance Notice given by the Proposing Party to the Recipient shall include a good faith estimate of the impact of the Material Change on the Estimated Milestone Schedule and an explanation of why such Material Change is being proposed.

  • Neither NYSEG nor National Grid shall be liable for failure to meet the Estimated Milestone Schedule, in whole or in part, or any estimated deadline or other date contained in the Estimated Milestone Schedule; provided, however, the Parties understand the need and agree to work cooperatively and expeditiously in good faith to meet the Estimated Milestone Schedule.

  • Estimated Milestone Schedule included in bid proposal documents.2.7 PRE-AWARD SUBMITTALSA.

  • Estimated Milestone Schedule Milestone Milestone Date Notice to Proceed TBD ECAA Approval Equipment Procurement Notice to Proceed + 8 Weeks Construction Mobilization Notice to Proceed + 40 weeks Substantial Completion Notice to Proceed + 60 weeks Final Completion Notice to Proceed + 70 weeks Contractor shall be given a day-for-day slip in the Work Milestone Schedule for a delay in the Funding Date beyond the date shown above.

  • Complete non-binding Estimated Milestone Schedule included in bid proposal documents.

  • Comparing the angles between regions to see the relative amounts of growth that occurred in each time step is now misleading.

Related to Estimated Milestone Schedule

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • Completion Schedule means the fulfilment of the Related Services by the Supplier in accordance with the terms and conditions set forth in the Contract;

  • Project Milestone means the project milestone set forth in Schedule-J;

  • Milestone Date means the date set against the relevant Milestone in the Implementation Plan;

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Milestone 1 means achievement of annual Net Sales of at least $20,000,000 during the Calendar Year ending on December 31, 2021.

  • Milestone means an event or task described in the Implementation Plan which must be completed by the corresponding date set out in such plan;

  • Development Schedule shall have the meaning set forth in Section 1.1.

  • Material Project EBITDA Adjustments means, with respect to each Material Project:

  • Milestone Events has the meaning set forth in Section 3.3 (Milestone Payments).

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Milestone Event has the meaning set forth in Section 8.4.

  • Work Schedule means the approved order and timeline for how the requirements of this contract, including Work on individual Units or groups of Units, will be fulfilled by the Contractor.

  • Timeline means the list of critical dates and actions included in the Introductory Materials.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Final Completion Date means the date on which Final Completion occurs.

  • Milestones means control points in the project that help to chart progress. Milestones may correspond to the completion of a key deliverable, allowing the next phase of the work to begin. They may also be needed at intermediary points so that, if problems have arisen, corrective measures can be taken. A milestone may be a critical decision point in the project where, for example, the consortium must decide which of several technologies to adopt for further development.