Facilities Study Report means that certain Facilities Study Report expected to be finalized as part of Developer’s interconnection request submitted and pending with the NYISO (NYISO Queue No. 543).
Facilities Study Report means that certain Facilities Study Report expected to be finalized pursuant to the Facilities Study Agreement by and among LS Power Grid New York, LLC, New York Power Authority, Company and NYISO dated July 19th, 2019 (the “Facilities Study Agreement”) as part of Developer’s interconnection request submitted and pending with the NYISO (NYISO Queue No. 556); the initial draft of such Facilities Study Report was delivered to NYISO on June 9th, 2020.
Facilities Study Report means that certain Class Year 19 Facilities Study - Part 1 Report for the 79.725MW Roaring Brook Wind Project (Queue #546), Version 3.0, dated 7/28/2020 and attached hereto as Exhibit A-1.

Examples of Facilities Study Report in a sentence

  • The Agreement has been entered into prior to the issuance of a Facilities Study Report with respect to the Transmission Project, with the intention of allowing Company Work to commence at the risk of the Developer as contemplated by the Agreement.

  • Interconnection Customer shall tender comments on the draft Interconnection Facilities Study Report within thirty (30) Calendar Days of receipt of the report.

  • Transmission Provider and Interconnection Customer shall negotiate concerning any disputed provisions of the appendices to the draft LGIA for not more than sixty (60) Calendar Days after tender of the final Interconnection Facilities Study Report.

  • For the avoidance of doubt: preparation, completion and delivery of the Facilities Study Report is not part of the Company Work under this Agreement.

  • The Company recognizes the Developer’s construction schedule and NYISO required in-service date of December 31, 2023 and will work under this Agreement to start tasks typically not initiated until after the completion of the applicable NYISO Facilities Study Report.


More Definitions of Facilities Study Report

Facilities Study Report means that certain Facilities Study Report for the Energy Highway: Segment B Transmission Interconnection Project (Queue #543), Version 3.0, dated 11/09/20, together with all appendices and exhibits attached thereto or referenced therein, and any revisions, updates, amendments, modifications or supplements thereto issued, made or entered into after the issuance of such Version 3.0 thereof.
Facilities Study Report means that certain Class Year 2019 Facilities Study - Part 1 Report For the 339.78 MW Alle Catt II Wind Project (Queue #596) Cattaraugus County, NY Final Draft, Version 1.0, together with all appendices and exhibits attached thereto or referenced therein (including, without limitation, the Technical Scope for Lime Lake Station - Alle Catt II Wind Project), and any revisions, updates, amendments, modifications or supplements thereto issued, made or entered into after the issuance of such Version 1.0 thereof.
Facilities Study Report means that certain Facilities Study - Part 1 Report for the 105.8 MW Number 3 Wind Project Final Draft, Version 4.0, to be issued at some time following the Effective Date, together with all appendices and exhibits attached thereto or referenced therein (including, without limitation, the Technical Scope for Waters Road Station - Number 3 Wind Project), and any revisions, updates, amendments, modifications or supplements thereto issued, made or entered into after the issuance of such Version 4.0 thereof.
Facilities Study Report means that certain Facilities Study Report for the NYPA GilboaNew Scotland Line #1 OPGW Installation, Version 1.1, dated 2/26/18 (NYPA GNS-1 OPGW Project, Queue #440), a copy of which is attached to this Agreement as Exhibit A-1.
Facilities Study Report means that certain Facilities Study Report for the KCE NY6 XXXX Facility 20 MW (Queue #759), Version 2.0, dated September 24, 2020.
Facilities Study Report means that certain Facilities Study Report For the Xxxxxx-Xxxxxx Series Reactor Transmission Interconnection Project (Queue #899), Final ,Version 2.0, dated 08/12/22, together with all appendices and exhibits attached thereto or referenced therein, and any revisions, updates, amendments, modifications, or supplements thereto issued, made or entered into after issuance of such Version 2.0 dated 08/12/22 .
Facilities Study Report means that certain Class Year 2019 Facilities Study - Part 1 Report For the 339.78 MW Alle Catt II Wind Project (Queue #596) Cattaraugus County, NY Final Draft, Version 1.0, together with all appendices and exhibits attached thereto or referenced therein (including, without limitation, the Technical Scope for Lime Lake Station