Examples of Optional Spare Parts in a sentence
Contractor shall be entitled to a Change Order pursuant to Article 9 to cover the additional costs of such Optional Spare Parts.
Owner shall make such procured Optional Spare Parts available to Contractor for use during its performance of the Work (as supplements for the Mandatory Spare Parts procured by Contractor pursuant to Section 3.6(f)(i)).
The Financial Supervisory Authority may issue further regulations on the submission of the reports referred to in subsection 1 and their handling in the stock exchange.
At least two (2) years prior to the scheduled completion of the Startup Tests or as otherwise agreed to in the Project Schedule, Owner shall identify to Contractor the Optional Spare Parts which Owner wants Contractor to procure.
Within one hundred and eighty (180) Days following receipt of Contractor’s list or as otherwise agreed to in the Project Schedule, Owners shall identify to Contractor the Optional Spare Parts which Owners want Contractor to procure, if any, and the Parties shall determine a mutually agreeable delivery schedule for such Optional Spare Parts.
Optional Spare Parts may be shared with other utilities in Owner’s sole discretion.
Within eighteen (18) months after finalization of the AP1000 Nuclear Power Plant design as specified in the Project Schedule, Contractor shall provide Owner with a list and the associated costs of Optional Spare Parts that are recommended by Contractor and vendors of Equipment comprising the Facility.
At Owner’s election, Owner may procure any Optional Spare Parts on its own, or, at least two years prior to the scheduled completion of the Start-up Tests, or as otherwise agreed, Owner may identify to Contractor which Optional Spare Parts Owner wants Contractor to supply to Owner.
Contractor shall have the right to use Owner’s Mandatory Spare Parts or Owner’s Optional Spare Parts for the Facility during the performance of the Work or to remedy a Warranty item, and Contractor shall promptly repair or replace any such spare part that it uses.
Owner may maintain certain Mandatory Spare Parts, (as well as any Optional Spare Parts it may choose to purchase), under a pooling agreement with a consortium of utilities that are constructing AP1000 Nuclear Power Plants.