Scheduled Commissioning Date or “SCD” of the Project shall mean [Insert Date];
Scheduled Commissioning Date means 12 (twelve) months from the Effective Date.
Scheduled Commissioning Date means 18 (Eighteen) months from the Effective Date.
Examples of Scheduled Commissioning Date in a sentence
Such extension of time by APDCL shall not affect the Commissioning of the Project within the Scheduled Commissioning Date.
Subject to other provisions of this Agreement, APDCL shall release the Performance Security, if any after eighteen (18) months from the Scheduled Commissioning Date.
More Definitions of Scheduled Commissioning Date
Scheduled Commissioning Date or “SCD” shall mean 9 months from the effective date as defined in Article 1 of PPA;
Scheduled Commissioning Date or “SCD” of the Project Shall mean date that is nine (9) Months from the Date of execution of this PPA between _PGVCL
Scheduled Commissioning Date or “SCD” shall mean date as on thirteen (13)/fifteen (15) months (as applicable) from the effective date of the SECI-SPD PPA;
Scheduled Commissioning Date or “SCD” : shall mean [Insert a date as on 18 months from the Effective Date];
Scheduled Commissioning Date means the actual commissioning date of respective unit(s) of the power Project where upon the Biogas Project Developer starts injecting power from the power Project to PSPCL grid / production of Bio CNG.
Scheduled Commissioning Date has the meaning as specified in Section A of Part I (Individual Terms);
Scheduled Commissioning Date means ……………… [Insert Date that is eighteen (18) months from the Effective Date of this Agreement];