Bonus for early completion Sample Clauses

Bonus for early completion. In the event that the Project Completion Date occurs prior to the Scheduled Completion Date, the Contractor shall be entitled to receive a payment of bonus equivalent to 0.03% (zero point zero three per cent) of the Contract Price for each day by which the Project Completion Date precedes the Scheduled Completion Date, but subject to a maximum of 5% (five per cent) of the Contract Price. Provided, however, that the payment of bonus, if any, shall be made only after the issue of the Completion Certificate. For the avoidance of the doubt, the Parties agree that for the purpose of determining the bonus payable hereunder, the Contract Price shall always be deemed to be the amount specified in Clause 19.1.1, and shall exclude any revision thereof for any reason. The Parties also agree that bonus shall be payable only if each work for which Extension of Time has been granted is completed within respective Extended Time.
AutoNDA by SimpleDocs
Bonus for early completion. (*) BONUS FOR EARLY COMPLETION If the Contractor achieves completion of Works in all respect prior to the time schedule stipulated in the SCC, the Employer shall pay to the Contractor the relevant sum, if mentioned specifically in SCC, as bonus for early completion. The bonus for early completion, if provided specifically in SCC, shall be payable to the maximum ceiling of 2 ½ % of the total contract price.
Bonus for early completion. If the Contractor achieves completion of Works in all respect prior to the time schedule stipulated in the SCC, the Employer shall pay to the Contractor the relevant sum, if mentioned specifically in SCC, as bonus for early completion. The bonus for early completion, if provided specifically in SCC, shall be payable to the maximum ceiling of 2 ½ % of the total contract price. (*) Partial earlier completion may not always produce net benefits to the Employer, for example where utilization of the completed Works requires (a) the fulfillment of all parts of the Contract (e.g. the training of personnel); or (b) the completion of all Sections (e.g. in pipeline laying, where early completion of the laying of pipeline would not be useful if the compressor is still under installation); or (c) certain seasonal effects to take place (e.g. onset of the rainy season, for impounding a reservoir); or (d) other circumstances. Also a more rapid drawdown of budgeted funds may be required. All such factors should be considered prior to the inclusion of a bonus clause in the Contract.
Bonus for early completion. 37.1 If the Supplier delivers all or part of the Goods before the period(s) specified in the Contract, the Purchaser shall, without prejudice to its other remedies under the Contract, add to the Contract Price as bonus, a sum equivalent to the percentage specified in SCC of the delivered price of the supplied Goods for each week or part thereof, up to a maximum sum of the percentage specified in SCC
Bonus for early completion. 10.6.1 Is a bonus to be payable? No
Bonus for early completion. In the event that the Project Completion Date occurs prior to the Scheduled Completion Date, the Contractor shall been titled to receive a payment of bonus equivalent to 0.03% (zero point zero three per cent) of the Contract Price for each day by which the Project Completion Date precedes the Scheduled Completion Date, butsubject to a maximum of 5% (five per cent) of the Contract Price. Provided, however, that the payment of bonus, if any, shall be made only after the issue of the Completion Certificate. For the avoidance of the doubt, the Parties agree that for the purpose of determining the bonus payable hereunder, the works shall always be deemed to be asspecified in this Contract Agreement but excluding the works deemed to be deletedfrom the scope of work under clause 8.3 of this Contract Agreement and the Contract Price shall always be deemed to be the amount specified in Clause 19.1 (i) after excluding the Contract Price of the Works deemed to be deleted from the Scope of Work under clause 8.3 of this Contract Agreement, and shall exclude any revision there of for any reason. The Parties also agree that bonus shall be payable only if each work for which Time Extension has been granted is completed with inspective Extended Time.
Bonus for early completion. If the Employer is in need of occupying the Project in early time, the payment of "Bonus for Early Completion " may be stated in the Appendix to Tender. Chapter Nine-Tests On Completion
AutoNDA by SimpleDocs
Bonus for early completion. 10.6.1 Is a bonus to be payable? No • If yes, the bonus for the Contract Works is: N/A ($ per Working Day) • If yes, bonuses for any Separable Portions are: N/A ($ per Working Day)
Bonus for early completion. In the event that the HOT RUN COMMENCEMENT -------------------------- occurs prior to the HOT RUN COMMENCEMENT DEADLINE, then NATIONAL agrees to pay to CONTRACTOR, a bonus (the "COMPLETION BONUS") determined in accordance with the requirements, and subject to the conditions, set forth below :
Bonus for early completion. If the Contractor finishes its Work during an outage before the end date of the Scheduled Outage Period, then for each day Owner is able to generate power from the affected Unit Contractor shall receive a bonus as follows: Morgantown: $ 35,000 per Unit per day Xxxxxxxxx: $15,000 per Unit per day Chalk Point: $25,000 per Unit per day