Common use of Force Majeure Delays Clause in Contracts

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

Appears in 2 contracts

Samples: Letter Agreement (New Century Financial Corp), Work Letter Agreement (Virtual Mortgage Network Inc)

AutoNDA by SimpleDocs

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

Appears in 2 contracts

Samples: Letter Agreement (California First National Bancorp), Industrial Lease (Cutter & Buck Inc)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 29.17 of the Original Lease.. ​

Appears in 1 contract

Samples: Office Lease (XOMA Corp)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 31.17 of the LeaseStandard Provisions.

Appears in 1 contract

Samples: Office Lease (Alteryx, Inc.)

Force Majeure Delays. For purposes of this Tenant Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 29.16 of the Lease.

Appears in 1 contract

Samples: Office Lease (Xponential Fitness, Inc.)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by many of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 38 of the Lease.

Appears in 1 contract

Samples: Work Letter Agreement (Borland Software Corp)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as “Force Majeure” is described in Paragraph 33 Section 26.03 of the Lease.. EXHIBIT C

Appears in 1 contract

Samples: Lease (Adamas Pharmaceuticals Inc)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord in the construction of any of the Office Improvements or Tenantthe Allowance Improvements, as which is not a Tenant Delay and which is caused by any of the case may be, as causes described in Paragraph 33 Section 31.17 of the Lease.

Appears in 1 contract

Samples: Work Letter Agreement (Gigamon LLC)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as “Force Majeure” is described in Paragraph 33 Section 26.03 of the Lease.. EXHIBIT C CURRENT PREMISES REMAINING FF&E Exhibit C-1

Appears in 1 contract

Samples: Lease (Adamas Pharmaceuticals Inc)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by many of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 32.15 of the Lease.

Appears in 1 contract

Samples: Office Lease (Willdan Group, Inc.)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 31.17 of the LeaseStandard Provisions.

Appears in 1 contract

Samples: Boxabl Inc.

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 Section 32.15 of the Lease.

Appears in 1 contract

Samples: Antenna License Agreement (Silicon Image Inc)

AutoNDA by SimpleDocs

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means shall mean any actual delay beyond the reasonable control of Lessor in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 28.D of the Lease.. SCHEDULE "1" to EXHIBIT E

Appears in 1 contract

Samples: Socket Communications Inc

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 Section 19(v) of the Lease.

Appears in 1 contract

Samples: Office Lease (Tandem Diabetes Care Inc)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means ” shall mean any actual delay beyond the reasonable control of Landlord in the construction of the Tenant Improvements, which is beyond not a Tenant Delay and which is caused by any of the reasonable control of Landlord or Tenant, as the case may be, as causes described in Paragraph 33 19(w) of the Lease.. EXHIBIT B

Appears in 1 contract

Samples: Office Lease (Somaxon Pharmaceuticals, Inc.)

Force Majeure Delays. For purposes of this Work Letter, "'Force Majeure -------------------- Delays" means ' shall mean any actual delay beyond the reasonable. control of Landlord in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord not a Tenant Delay and which is caused by, without limitation, any one or Tenant, as the case may be, as described in Paragraph 33 more of the Lease.following:

Appears in 1 contract

Samples: Letter Agreement (2themart Com Inc)

Force Majeure Delays. For purposes of this Work LetterLetter Agreement, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, which Improvements that is beyond the reasonable control of Landlord or Tenant, as the case may be. Notwithstanding the foregoing, as described in Paragraph 33 delays or failures to perform resulting from lack of funds shall not be deemed delays beyond the Leasereasonable control of a party.

Appears in 1 contract

Samples: Work Letter Agreement (CombiMatrix Corp)

Force Majeure Delays. For purposes of this Work Letter, "Force -------------------- Majeure -------------------- Delays" means any actual delay in the construction of the Expansion Space Tenant Improvements, Improvements (including required Building permits) which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

Appears in 1 contract

Samples: Work Letter Agreement (Interplay Entertainment Corp)

Force Majeure Delays. For purposes of this Work Letter, "Force Majeure -------------------- Delays" means any actual delay in the construction of the Tenant Improvements, permits) which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

Appears in 1 contract

Samples: Work Letter Agreement (Interplay Entertainment Corp)