Common use of Progress Reports Clause in Contracts

Progress Reports. At monthly intervals after approval of the Program chart, the contractor is to submit to the Engineer and the purchaser written detailed progress reports in triplicate in an approved form, indicating the stage reached in the design, ordering of material, manufacture and delivery of all components of the material. The reports should include details of any delays and the remedial action proposed. These reports are to be forwarded promptly so that on receipt by the engineer the information contained therein is not more than seven days out of date.

Appears in 57 contracts

Samples: www.ideco.com.jo, Second Time, www.ideco.com.jo

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.