Critical Path definition

Critical Path means those Trade Contractor Work activities identified on the Construction Schedule which, if delayed, will cause a corresponding Delay in the Substantial Completion Date.
Critical Path means the sequence of activities from the start of the Work to Substantial Completion of the Project for which any delay in the completion of these activities will delay achieving Substantial Completion.
Critical Path means the path through the project schedule indicating the minimum time in which it is possible to complete the Work, and the tasks that, if delayed, will delay Substantial Completion of the Work."

Examples of Critical Path in a sentence

  • The Design-Build Contractor is entitled to an extension of Completion Deadlines if the hazmat discovery results in delays to a Critical Path activity.

  • Except with respect to Work done or materials used as described in the foregoing sentence, if Work exposed or examined under this Section 5.4.3 is in conformance with the requirements of the Contract Documents, then any delay in any Critical Path from uncovering, removing and restoring Work shall be considered a TxDOT- Caused Delay, and DB Contractor shall be entitled to a Change Order for the cost of such efforts and recovery of any delay to any Critical Path occasioned thereby.

  • The Design-Build Contractor is not entitled to any time extensions on account of delays attributable to utilities, except for delays affecting the Critical Path due to (a) New Utilities (not existing as of the Proposal date) requiring adjustment and (b) uncooperative utility owners that do not enter into adjustment agreements.

  • Utility Owner Delay" shall mean a delay to a Critical Path that is directly attributable to a Utility Owner's failure to cooperate with DB Contractor in performing Utility Adjustment Work within the time period reasonably scheduled by DB Contractor for performance of such work, where DB Contractor and Utility Owner have not yet executed a Utility Agreement addressing such Utility Adjustment Work.

  • If the Work exposed or examined is not in conformance with the requirements of the Contract Documents, then uncovering, removing and restoring the Work and recovery of any delay to any Critical Path occasioned thereby shall be at Developer’s cost and Developer shall not be entitled to any adjustment to the Price or any Completion Deadline or any other relief.


More Definitions of Critical Path

Critical Path means the activities and durations associated with the longest chain(s) of
Critical Path means the longest sequence of activities in a project plan which must be completed on time for that project to complete by the stated due date.
Critical Path means the schedule path with the least amount of total float which constitutes the longest continuous sequence of interrelated activities depicting Work from an NTP to completion of a final or designated intermediate Milestone.
Critical Path. The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no total float.
Critical Path means the sequence of activities from the start of the Work to the Substantial Completion of the Project. Any delay in the completion of these activities will extend the Substantial Completion date.
Critical Path means the sequence of activities yielding the longest path in a critical path method (CPM) schedule.
Critical Path means the sequential construction tasks (each of a particular duration) that results in the least amount of time required to complete a project.