Period of delay definition

Period of delay means the number of days commencing on the day fixed by the Articles of Agreement for completion of the work and ending on the day immediately preceding the day on which the work is completed but does not include any day within a period of extension granted pursuant to GC35.1, and any other day on which, in the opinion of the Engineer, completion of the work was delayed for reasons beyond the control of the Contractor.
Period of delay means the days during which the Service Provider fails to complete the Services or any part of the Services.
Period of delay means the number of days commencing on the day fixed by the Articles of Agreement for completion of the Work and ending on the day

Examples of Period of delay in a sentence

  • Period of delay in payment authorising 8.7…..months termination by Vendor.

  • Nil Nilc)The amount of interest due and payable for the Period of delay in making payment (which have been paid but beyond the appointed during period) but without adding the interest specified under the Micro, Small and Medium Enterprises Development Act, 2006.

  • Menegaki, 2017, Geophysical Measurements to Detect Ahead of Bucket Wheel Excavators the Problematic Hard Formations in Coal Mines, Near surface Geosciences 2017, 23rd European Meeting of Environmental and Engineering Geophysics.

  • Period of delay, for the purpose of payment of interest, will be calculated as the gap between the defined date of credit of cheque and the actual date of credit.

  • In case, either of the party, does not reach for price settlement (as per clause 7 of TOR), none of the party can claim any compensation/ Damages on account of non-fulfillment of contract quantity.

  • We observed that there were substantial delay in submission of research reports and details of which are given in Table 9.2. Table 9.2: Period of delay in submission of Research Reports Delay in submission of research reports(Source: Details furnished by the Department) Non-submission of reports in large numbers cast doubt about whether research activities permitted were taken up at all by the concerned individuals or were completed as stipulated.

  • The owner is also responsible for maintaining any required storm water detention to ensure storage capacity is maintained and the system is functioning properly.

  • Period of delay taken from the due date of receipt of accounts i.e. 30 June of the ensuing financial year till 30 June 2015.

  • Period of delay taken from the due date of receipt of accounts i.e. 30 June of the ensuing financial year till 30 June 2016.

  • The formula usually used is as follows:- H.O./Profit Percentage x Contract Sum x Period of delay (in weeks)100 Contract Period (e.g. in weeks) A caveat should, however, be entered in regard to the profit element in the above formula.


More Definitions of Period of delay

Period of delay means the period commencing on the day fixed by Article I of the Articles of Agreement for completion of the Work or any portion thereof or such subsequent day, if any, to which the time for completion has been extended under subsection (1) and ending on the day immediately preceding the day on which the Work or portion thereof is completed.
Period of delay means the period of time between the Scheduled Date of Completion and the actual date on which commercial operations or tenant/owner occupancy commenced or could have commenced; however, not exceeding such delay as would result if the loss or damage were repaired or replaced with the exercise of due diligence and dispatch, but in no event exceeding the Period of Indemnity stated in the Declarations for all indemnifiable Occurrences combined. The Period of Delay shall not be terminated by the expiration or cancellation of the Policy with respect to indemnity payable hereunder in direct consequence of insured loss or damage occurring prior to such expiration or cancellation.
Period of delay means the number of days commencing on the day fixed by the Contract for
Period of delay means the number of days commencing on the Occupancy Date and ending on the day immediately preceding the day on which the Demised Premises has been certified for occupancy but does not include any day in which, in the opinion of the Agency, completion of the Work was delayed for reasons beyond the control of the Lessor.
Period of delay means the period commencing on the day fixed by Article I of the Articles of Agreement for completion of the work or any portion thereof or such subsequent day, if any, to which the time for completion has been extended under subsection (1) and ending on the day immediately preceding the day on which the work or portion thereof is completed.
Period of delay means a period of two years beginning with the date of registration of a rent;

Related to Period of delay

  • Period of Work means the time during which an employee is at the disposal of the employer;

  • Project Period means the period es- tablished in the award document dur- ing which Federal sponsorship begins and ends.

  • Commissioning Period means, with respect to each Subproject, the period commencing upon the first delivery of Feed Gas to the Subproject in accordance with Sections 4.8 and 11.1 of the Agreement continuing through achievement of RFSU, commissioning, Start Up, Performance Testing and achievement of Substantial Completion for such Subproject.

  • Interruption Period shall have the meaning set forth in Section 5 hereof.

  • Operation Period means the period commencing from COD and ending on the Transfer Date;

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;

  • Production Period is the period that for winter cereal advances commences October 1, 2021 and terminates September 30, 2023; for advances on all other field crops, honey, hogs, goats, sheep and lambs commences April 1, 2022 and terminates September 30, 2023; and for advances on cattle, continuous flow cattle, and bison commences on April 1, 2022 and terminates on March 31, 2024.

  • Employees working on the project means laborers, workers, and mechanics employed directly upon the site of work.

  • Period of Severance means a continuous period of time during which an Employee is not employed by the Employer. Such period begins on the date the Employee retires, quits or is discharged, or if earlier, the twelve (12) month anniversary of the date on which the Employee was otherwise first absent from service.

  • Curtailment Period means the period of time during which Seller reduces generation from the Project, pursuant to a Curtailment Order. The Curtailment Period shall be inclusive of the time required for the Project to ramp down and ramp up; provided that such time periods to ramp down and ramp up shall be consistent with the Ramp Rate designated in the Cover Sheet.

  • Period of restoration means the period of time that:

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Development Period means the period from the date of this Agreement until the Appointed Date;

  • Leave Year means the period during which the Agency Worker accrues and may take statutory leave commencing on the date that the Agency Worker starts an Assignment or a series of Assignments;

  • Scheduled Commercial Operation Date shall have the meaning ascribed to it in Clause 5.4.1;

  • Contract Term means period of performance set forth in the paragraph entitled “Term” contained in Exhibit E.

  • Working level month (WLM) means an exposure to 1 working level for 170 hours (2,000 working hours per year divided by 12 months per year is approximately equal to 170 hours per month).

  • Period of Service means the aggregate of all periods of service commencing with an Employee's first day of employment or reemployment with the Employer or an Affiliated Employer and ending on the first day of a Period of Severance, or for benefit accrual purposes, ending on the severance from service date. The first day of employment or reemployment is the first day the Employee performs an Hour of Service. An Employee who incurs a Period of Severance of twelve (12) months or less will also receive service-spanning credit by treating any such period as a Period of Service for purposes of eligibility and vesting (but not benefit accrual). For purposes of benefit accrual, a Participant's whole year Periods of Service is equal to the sum of all full and partial periods of service, whether or not such service is continuous or contiguous, expressed in the number of whole years represented by such sum. For this purpose, fractional periods of a year will be expressed in terms of days.

  • Principal Period of Maintenance means any nine consecutive hours per day (usually between the hours of 7:00 a.m. and 6:00 p.m.) as selected by the State, including an official meal period not to exceed one hour, Monday through Friday, excluding holidays observed at the installation.

  • Contract Year means each period of twelve (12) consecutive months during the Initial Term of this Agreement, with the first Contract Year commencing on the Effective Date, and with each subsequent Contract Year commencing on the anniversary of the Effective Date.

  • Contract Transition Period means the 90 day transition as defined in Section F of this Contract.

  • Period of Agreement means 5 years from the date of Final acceptance of the Project.

  • Budget Period means the fiscal period for which a budget is prepared.

  • Peak Period means the time between 6 a.m. and 10 p.m. (April through September) or between 7 a.m. and 11 p.m. (October through March) on all days except Saturdays and Sundays, which daily time period will be subject to change from time to time at the Company's option. This change would occur after no less than ten (10) days notice has been given to all Customers who would be affected, and to the Commission.

  • Operating Period for any Element of the Project shall mean the period from (and including) the COD of such Element of the Project, up to (and including) the Expiry Date and for the Project, shall mean the period from (and including) the COD of the Project, up to (and including) the Expiry Date;

  • Promotion Period means the period the Promotion is open, as specified in clause 5.1.