Financial Evaluation. 50.4 All clarification requests shall remind Tenderers of the need for confidentiality and that any breach of confidentiality on the part of the Tenderer may result in their Tender being non- responsive.
51.1 Provided that the Tender is responsive, TEC shall correct arithmetical errors on the following basis:
(a) If there is a discrepancy between the unit price and the line item total that is obtained by multiplying the unit price by the quantity, the unit price shall prevail and the line item total shall be corrected, unless in the opinion of the TEC there is an obvious misplacement of the decimal point in the unit price, in which case the total price as quoted willgovern and the unit price will be corrected;
(b) If there is an error in a total corresponding to the addition or subtraction of subtotals, the subtotals shall prevail and the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the amount in words shall prevail, unless the amount expressed in words is related to an arithmetic error, in which case the amount in figures shall prevail subject to (a) and (b) above.
51.2 TEC shall correct the arithmetic errors and shall promptly notify the concerned Tenderer(s), if the Tenderer does not accept the correction of arithmetic errors, its Tender shall be rejected.
52.1 TEC will evaluate each Tender that has been determined, up to this stage of the evaluation, to be responsive to the requirements set out in the Tender Document.
52.2 To evaluate a Tender, TEC will consider the following:
(a) Tender price for Item(s) or Lot
(b) adjustment for correction of arithmetical errors as stated under ITT SubClause 51.2;
(c) adjustment for application of the methodology for determining the equivalent lot value, as stated under ITT Sub Clause 23.8, if any;
(d) adjustment for application of the economic factors, as stated under ITT SubClause 52.6, if any;
(e) adjustmentin order to take into consideration the unconditional discounts and methodology for application of the discount offered for being awarded more than one lot, as stated under ITT SubClauses 24.11 and 24.12, if any.
(f) In view of Framework contract, the quoted rate shall not be more than the market price pursuant to rule 89(3). Market Price means Price of goods available in the market plus