Acceptance of Installation. 12.1 If installation of the Products is part of this Contract, Supplier shall notify Buyer when the Products installed will be ready for testing and acceptance, inviting Buyer to attend Supplier’s standard tests or such tests as may have been agreed upon in the Contract to demonstrate compliance with the agreed specifications and/or to inspect the installation work. 12.2 If Buyer fails to attend the testing on the date notified, Supplier will commence with the tests according to Supplier’s standard test procedures and these tests shall be considered performed in the presence of Buyer and acceptance shall in such case take place on the basis of the results stated in the test certificate signed by Supplier. 12.3 If Xxxxx rejects the Products installed it should submit to Supplier the reasons for such rejection in detail and in writing within 10 days after completion of the acceptance tests concerned. If, within Supplier’s reasonable opinion, the rejection is justified, Supplier shall as a sole remedy correct the shortcomings as soon as possible and the relevant parts of the acceptance test shall be repeated within a reasonable period of time in conformity which the procedures outlined above. 12.4 Upon acceptance of the Products, Buyer will sign the acceptance certificate. If, within 10 days after completion of the acceptance test, Supplier has not received the acceptance certificate signed by Buyer or a report with a justified rejection, the Products installed shall be deemed accepted by Buyer. 12.5 Minor defects or deviations not affecting the operational use of the Products installed shall be stated in the acceptance certificate but shall not obstruct or suspend acceptance. Supplier undertakes to remedy such defects as soon as reasonably possible.
Appears in 3 contracts
Samples: Terms and Conditions of Sale and Supply, Terms and Conditions of Sale and Supply, Terms and Conditions of Sale and Supply
Acceptance of Installation. 12.1 If In case of installation of the Products is part of this ContractProducts, Supplier shall notify Buyer when the Products installed will be ready for testing and acceptance, inviting Buyer to attend Supplier’s standard tests or such tests as may have been agreed upon in the Contract to demonstrate compliance with the agreed specifications and/or to inspect the installation work.
12.2 . If Buyer fails to attend the testing on the date notified, Supplier will commence with the tests according to Supplier’s standard test procedures and these tests shall be considered performed in the presence of Buyer and acceptance shall in such case take place on the basis of the results stated in the test certificate signed by Supplier.
12.3 If Xxxxx . In case Buyer rejects the Products installed it should submit to Supplier the reasons for such rejection in detail and in writing within 10 days after completion of the acceptance tests concerned. If, within Supplier’s reasonable opinion, the rejection is justified, Supplier shall as a sole remedy correct the shortcomings as soon as possible and the relevant parts of the acceptance test shall be repeated within a reasonable period of time in conformity which the procedures outlined above.
12.4 . Upon acceptance of the Products, Buyer will sign the acceptance certificate. If, If within 10 days after completion of the acceptance test, test Supplier has shall not have received the acceptance certificate signed by Buyer or a report with a justified rejection, the Products installed shall then be deemed considered as having been accepted by Buyer.
12.5 . Minor defects or deviations not affecting the operational use of the Products installed shall be stated in the acceptance certificate certificate, but shall not obstruct or suspend acceptance. Supplier undertakes to remedy such defects as soon as reasonably possible.
Appears in 1 contract
Samples: Service Contract
Acceptance of Installation. 12.1 If In case of installation of the Products is part of this ContractProducts, Supplier shall notify Buyer when the Products installed will be ready for testing and acceptance, inviting Buyer to attend Supplier’s standard tests or such tests as may have been agreed upon in the Contract to demonstrate compliance with the agreed specifications and/or to inspect the installation work.
12.2 If Buyer fails to attend the testing on the date notified, Supplier will commence with the tests according to Supplier’s standard test procedures and these tests shall be considered performed in the presence of Buyer and acceptance shall in such case take place on the basis of the results stated in the test certificate signed by Supplier.
12.3 If Xxxxx In case Buyer rejects the Products installed it should submit to Supplier the reasons for such rejection in detail and in writing within 10 days after completion of the acceptance tests concerned. If, within Supplier’s reasonable opinion, the rejection is justified, Supplier shall as a sole remedy correct the shortcomings as soon as possible and the relevant parts of the acceptance test shall be repeated within a reasonable period of time in conformity which the procedures outlined above.
12.4 Upon acceptance of the Products, Buyer will sign the acceptance certificate. If, If within 10 days after completion of the acceptance test, test Supplier has shall not have received the acceptance certificate signed by Buyer or a report with a justified rejection, the Products installed shall then be deemed considered as having been accepted by Buyer.
12.5 Minor defects or deviations not affecting the operational use of the Products installed shall be stated in the acceptance certificate certificate, but shall not obstruct or suspend acceptance. Supplier undertakes to remedy such defects as soon as reasonably possible.
Appears in 1 contract
Acceptance of Installation. 12.1 If 13.1 In case of installation of the Products is part of this Contract, Supplier shall notify Buyer when the Products installed will be ready for testing and acceptance, inviting Buyer to attend Supplier’s standard tests or such tests as may have been agreed upon in the Contract to demonstrate compliance with the agreed specifications and/or to inspect the installation work.
12.2 13.2 If Buyer fails to attend the testing on the date notified, Supplier will commence with the tests according to Supplier’s standard test procedures and these tests shall be considered performed in the presence of Buyer and acceptance shall in such case take place on the basis of the results stated in the test certificate signed by Supplier.
12.3 13.3 If Xxxxx Buyer rejects the Products installed it should submit to Supplier the reasons for such rejection in detail and in writing within 10 days after completion of the acceptance tests concerned. If, within Supplier’s reasonable opinion, the rejection is justified, Supplier shall as a sole remedy correct the shortcomings as soon as possible and the relevant parts of the acceptance test shall be repeated within a reasonable period of time in conformity which the procedures outlined above.
12.4 13.4 Upon acceptance of the Products, Buyer will sign the acceptance certificate. If, within 10 days after completion of the acceptance test, Supplier has not received the acceptance certificate signed by Buyer Xxxxx or a report with a justified rejection, the Products installed shall be deemed accepted by Buyer.
12.5 13.5 Minor defects or deviations not affecting the operational use of the Products installed shall be stated in the acceptance certificate but shall not obstruct or suspend acceptance. Supplier undertakes to remedy such defects as soon as reasonably possible.
Appears in 1 contract