Active Operations Period Sample Clauses
Active Operations Period. During this period the Project Monitoring Consultant would monitor, in accordance with Good Industry Practice, the operations and maintenance activities undertaken by the Concessionaire so as to ensure compliance with the O&M Requirements. The specific activities to be undertaken would include the following:
(a) Provide administration of the contract in full and in complete accordance with applicable laws;
(b) Act on the CNP’s behalf as the CNP’s representative regarding all contact with the Concessionaire unless expressly indicated otherwise;
(c) Designate tests on materials and/or equipment;
(d) Review and approve test results and materials and/or equipment used;
(e) Interpret the requirements of the contract and make decisions regarding performance of the Concessionaire. The PMC shall inform and advise the CNP, in a timely manner all matters relating to the execution, progress, and completeness of works;
(f) Reject work which fails to comply with the specifications and requirements of the Agreement. Whenever considered necessary or advisable to ensure correction of defective work, the PMC may require inspection or testing of such work, whether or not such work be then fabricated, installed, or completed;
(g) Review, approve or disapprove drawings, samples, and other submissions of the Concessionaire to determine compliance and conformance with the requirements of the Agreement;
(h) Provide the services of a full time resident project representative during the period commencing from 7 seven days from the date of appointment of the PE until the expiry of the PMC’s appointment;
(i) In addition to the daily responsibilities, conduct a general inspection of the Project Facilities at least once a month and as and when exigencies require to ascertain conformity with Construction Requirements and O&M Requirements;
(j) Provide the services of experts to check the quality of materials and the workmanship during the construction of the Landfill Facility
(k) Inspect the quality of compost being sold or otherwise disposed outside the Site
(l) Inspect and certify composition of the Residual Inert Matter
(m) Address issues relating to specific site conditions, design modifications, or Concessionaire disputes.
(n) Review the O&M Plans submitted by the Concessionaire from time to time and assist the Concessionaire in finalising the same. The Project Monitoring Consultant shall also consult CNP prior to finalisation of the O&M Plans;
(o) Periodically review the O&M Manua...
Active Operations Period. During this period the Project Engineer would monitor, in accordance with Good Industry Practice, the operations and maintenance activities undertaken by Concessionaire so as to ensure compliance with the O&M Requirements. The specific activities to be undertaken would include the following: Provide administration of the contract in full and in complete accordance with applicable laws; Act on the Concessioning Authority’s behalf as the Concessioning Authority’s representative regarding all contact with the Concessionaire unless expressly indicated otherwise; Interpret the requirements of the contract and make decisions regarding performance of Concessionaire. The PE shall inform and advise the Concessioning Authority’s, in a timely manner all matters relating to the execution, progress and completeness of works; Reject work, which fails to comply with the specifications and requirements of the Agreement. Whenever considered necessary or advisable to ensure correction of defective work, the PE may require inspection or testing of such work, whether or not such work be then fabricated, installed, or completed; Review submission of Concessionaire to determine compliance and conformance with the requirements of the Agreement; Provide the services representative during the period commencing from 7 (seven) days from the date of nomination of the PE until the expiry of the PE’s nomination. In addition to conduct a general inspection of the Project Facilities at least once a month and as and when exigencies require to ascertain conformity with Construction Requirements and O&M Requirements;