Common use of Add new 10 Clause in Contracts

Add new 10. 3.9 (a) the event in respect of which the extension of time is sought must be one listed in 10.3.1; (b) the event in respect of which the extension of time is sought must have caused, or will cause, actual delay to Practical Completion of the Contract Works. No extension of time will be granted unless the delay has affected the critical path of the Contract Works such that Practical Completion cannot be achieved by the Due Date for Completion; and (c) where the Contractor suffers delay in completion of the Contract Works which is caused by two or more events, at least one of which entitles the Contractor to an extension of time ("Valid Event") and at least one of which does not entitle the Contractor to an extension of time ("Invalid Event"), the Contractor shall only be entitled to the period of extension attributable to the Valid Event(s) which exceeds any period of extension attributable to the Invalid Event(s).

Appears in 10 contracts

Samples: Major Works Contract, Major Works Contract, Major Works Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!