Adjustment for Variations. 12.2.1 If the Council instructs a Variation, the Contract Sum is adjusted by adding or deducting (as the case requires) the value of the Variation as agreed between the Contractor and the Council. However, the Contract Sum must not be increased unless: 12.2.1.1 the Council has expressly stated in writing that the instruction is a Variation; 12.2.1.2 the Council has expressly stated in writing that the Contract Sum will be adjusted for the Variation; or 12.2.1.3 the works carried out are deemed a Variation under clause 11.7.
Appears in 2 contracts
Samples: Minor Works Agreement, Works Agreement
Adjustment for Variations. 12.2.1 If the Council instructs a Variation, the Contract Sum is adjusted by adding or deducting (as the case requires) the value of the Variation as agreed between the Contractor and the Council. However, However the Contract Sum must not be increased unless:
12.2.1.1 12.2.1 the Council has expressly stated in writing that the instruction is a Variation;
12.2.1.2 12.2.2 the Council has expressly stated in writing that the Contract Sum will be adjusted for the Variation; or
12.2.1.3 12.2.3 the works carried out are deemed a Variation under clause 11.7.
Appears in 1 contract
Samples: Minor Works Agreement
Adjustment for Variations. 12.2.1 If the Council instructs a Variation, the Contract Sum is adjusted by adding or deducting (as the case requires) the value of the Variation as agreed between the Contractor and the Council. However, However the Contract Sum must not be increased unless:
12.2.1.1 : the Council has expressly stated in writing that the instruction is a Variation;
12.2.1.2 ; the Council has expressly stated in writing that the Contract Sum will be adjusted for the Variation; or
12.2.1.3 or the works carried out are deemed a Variation under clause 11.7.
Appears in 1 contract
Samples: Minor Works Agreement
Adjustment for Variations. 12.2.1 If the Council instructs a Variation, the Contract Agreed Sum is adjusted by adding or deducting (as the case requires) the value of the Variation as agreed between the Contractor and the Council. However, the Contract Agreed Sum must not be increased unless:
12.2.1.1 15.2.1 the Council has expressly stated in writing that the instruction is a Variation;
12.2.1.2 15.2.2 the Council has expressly stated in writing that the Contract Agreed Sum will be adjusted for the Variation; or
12.2.1.3 15.2.3 the works carried out are deemed a Variation under clause 11.714.7.
Appears in 1 contract
Samples: Works Agreement
Adjustment for Variations. 12.2.1 If the Council instructs a Variation, the Contract Sum is adjusted by adding or deducting (as the case requires) the value of the Variation as agreed between the Contractor Supplier and the Council or as determined by the Council. However, However the Contract Sum must not be increased unless:
12.2.1.1 17.2.1 the Council has expressly stated in writing that the instruction is a Variation;
12.2.1.2 17.2.2 the Council has expressly stated in writing that the Contract Sum will be adjusted for the Variation; or
12.2.1.3 17.2.3 the works carried out are deemed a Variation under clause 11.716.7.
Appears in 1 contract
Samples: Construction Contract