Adjustment of Scheduled Substantial Completion Date. If Contractor’s Baseline Schedule submitted pursuant to Section 13.1.2 shows a projected date for Substantial Completion more than thirty (30) days earlier than the Scheduled Substantial Completion Date, Contractor agrees that Owner may, at no cost to Owner, decrease the Scheduled Substantial Completion Date by issuance of an appropriate Change Order changing the Scheduled Substantial Completion Date to the date reflected in the Baseline Schedule. The specific intent of this Section 13.1.4 is to ensure that Contractor does not have a right to seek recovery from Owner on the grounds that it was entitled to achieve Substantial Completion of the Project earlier than the Scheduled Substantial Completion Date.
Appears in 3 contracts
Samples: Design Build Contract, www.mwaa.com, www.mwaa.com
Adjustment of Scheduled Substantial Completion Date. If Contractor’s Baseline Schedule submitted pursuant to Section 13.1.2 shows a projected date for Substantial Completion more than thirty (30) days earlier than the Scheduled Substantial Completion Date, Contractor agrees that Owner may, at no cost to Owner, decrease the Scheduled Substantial Completion Date by issuance of an appropriate Change Order changing the Scheduled Substantial Completion Date to the date reflected in the Baseline Schedule. The specific intent of this Section 13.1.4 is to ensure that Contractor does not have a right to seek recovery from Owner on the grounds that it was entitled to achieve Substantial Completion of the Project earlier than the Scheduled Substantial Completion Date.
Appears in 1 contract
Samples: metwashairports.com