Common use of Adjustments to GMP Clause in Contracts

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record and the Owner’s Authorized Representative promptly after becoming aware of any Scope Change. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record within the earlier of: (a) 10 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 CM/GC shall work with Engineer of Record to reconcile all differences in its GMP Change Request with the Engineer of Record within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies the reason for differences in the GMP Change Request and the Engineer of Record’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 3 contracts

Samples: Cm/Gc Contract, Construction Manager/General Contractor Contract, Cm/Gc Contract

AutoNDA by SimpleDocs

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record and the Owner’s Authorized Representative Owner promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative Owner and to Engineer of Record Design Consultant within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Engineer of Record Design Consultant to reconcile all differences in its GMP Change Request with the Engineer of Record Design Consultant within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record Design Consultant have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordDesign Consultant’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 2 contracts

Samples: Construction Manager/General Contractor Contract, Construction Manager/General Contractor (Cm/Gc) Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 The CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of the CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). The CM/GC shall deliver any such GMP Change Request to Engineer of Record the architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in the CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 The CM/GC shall submit its GMP Change Requests as soon as possible, and the CM/GC shall not be entitled to claim a GMP increase unless the CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record architect within the earlier of: of (a) 10 Days 14 days after the CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which the CM/GC intends to claim a Scope Change; or and (c) in any event, prior to the CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 The CM/GC shall work with Engineer of Record architect to reconcile all differences in its GMP Change Request with the Engineer of Record architect within seven Days days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s architect's position. The CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 2 contracts

Samples: Construction Manager/General Contractor Contract, Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 CM/GC 7.2.1 Contractor shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GCContractor, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC Contractor shall deliver any such GMP Change Request to Engineer of Record the Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in Contractor’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 CM/GC 7.2.3 Contractor shall submit its GMP Change Requests as soon as possible, and CM/GC Contractor shall not be entitled to claim a GMP increase unless CM/GC Contractor submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 Days 14 days after CM/GC Contractor has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC Contractor intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's Contractor’s signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's ’s basis for such request, which may include, for example, reduction of the CM/GC's Contractor’s Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 CM/GC 7.2.5 Contractor shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC Contractor and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC Contractor shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC Contractor claim for a GMP increase.

Appears in 2 contracts

Samples: Construction Services Contract, Emergency Construction Services Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 CM/GC shall 7.2.1 Contractor will review subsequent iterations of modifications to the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GCContractor, they the modifications result in a Scope Change so that it can be determined if warranting an adjustment to the GMP is warrantedGMP. 8.1.2 Changes 7.2.2 Contractor-requested changes to the GMP shall will be initiated by written notice by one party to the other ("Contractor’s delivery of a GMP Change Request"). CM/GC shall Contractor will deliver any such GMP Change Request to Engineer of Record and the OwnerCity’s Authorized Representative and the Architect promptly after becoming aware of any Scope ChangeChange if, in Contractor’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall will include a Contractor’s proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 CM/GC shall 7.2.3 Contractor will submit its GMP Change Requests as soon as possible, and CM/GC shall Contractor will not be entitled to claim a GMP increase unless CM/GC submitted Contractor submits a GMP Change Request to the OwnerCity’s Authorized Representative and to Engineer of Record the Architect within the earlier of: of (a) 10 seven (7) Days after CM/GC Contractor has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change.information 8.1.4 The Owner 7.2.4 City may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall will include the Owner's City’s basis for such request, which may include, for example, reduction of the CM/GC's Contractor’s Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or or any unused Allowances. 8.1.5 CM/GC shall 7.2.5 Contractor will work with Engineer of Record the Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven (7) Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC Contractor and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC shall Contractor will submit the Reconciled GMP Change Request to the OwnerCity, which submission shall will be a condition to any CM/GC Contractor claim for a GMP increase.

Appears in 1 contract

Samples: Cm/Gc Construction Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's ’s signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's ’s basis for such request, which may include, for example, reduction of the CM/GC's ’s Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 The CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party Party to the other ("GMP Change Request"). The CM/GC shall deliver any such GMP Change Request to Engineer of Record the Architect, Owner’s Consultant, and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in the CM/GC's opinion, the Scope Change constitutes grounds for adjustment of the GMP. Any GMP Change Request shall must include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 The CM/GC shall submit its all GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative Representative, Owner’s Consultant, and to Engineer of Record the Architect within the earlier of: of (a) 10 30 Days after the CM/GC has received the information constituting the basis for the claim, ; or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which the CM/GC intends to claim a Scope Change; or (c) in any event, prior to the CM/GC's signing of a Change Order for the Scope Change. 8.1.4 7.2.4 The Owner may, at any time, submit a written GMP Change Request to CM/GC requesting a reduction of the GMP, which shall must include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or or any unused Allowances. 8.1.5 7.2.5 The CM/GC shall work with Engineer of Record the Architect as needed to reconcile all any differences in its GMP Change Request with the Engineer of Record within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that or issues between the CM/GC and the Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies the reason for differences Architect in the CM/GC’s GMP Change Request and the Engineer of Record’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.within seven

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 15 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's ’s signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's ’s basis for such request, which may include, for example, reduction of the CM/GC's ’s Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this ContractCM/GC Agreement, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they changes are a result of an evolution of the design documents (with any change in cost to be covered by Contingency) or whether the changes represent a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Architect/Engineer of Record within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for examplebut are limited to, a reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Architect/Engineer of Record as needed to reconcile all differences in its GMP Change Request with the Architect/Engineer of Record within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Architect/Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s Architect/Engineer's position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Agreement

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.1 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC Contractor shall deliver any such GMP Change Request to Engineer of Record and the Owner’s Authorized Representative promptly after becoming aware of any Scope Change. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue.Architect 8.1.3 CM/GC 7.2.2 Contractor shall submit its GMP Change Requests as soon as possible, and CM/GC Contractor shall not be entitled to claim a GMP increase unless CM/GC Contractor submitted a GMP Change Request to the Owner’s Authorized Representative, Owner’s Representative and to Architect / Engineer of Record within the earlier of: of (a) 10 30 Days after CM/GC Contractor has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC Contractor intends to claim a Scope Change; or (c) and in any event, prior to CM/GCContractor's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.3 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GCContractor's Contingency after further development of the Plans and Specifications that form the basis for the original GMP AmendmentGMP, and/or unused Allowances. 8.1.5 CM/GC 7.2.4 Contractor shall work with Architect / Engineer of Record and Owner’s Representative to reconcile all differences in its GMP Change Request with the Engineer of Record within seven Days (7) calendar days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC Contractor and the Architect / Engineer of Record and Owner’s Representative have verified that their assumptions about the various categories are all the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordArchitect / Engineer's and Owner’s Representative’s position. CM/GC Contractor shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC Contractor claim for a GMP increase.

Appears in 1 contract

Samples: Public Improvement Agreement

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only with written agreement between the Owner and CM/GC and: (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then Adjustments to the GMP will occur only in accordance with the following procedure: 8.1.1 6.2.1 CM/GC shall review subsequent iterations of changes to the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 6.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 6.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record within the earlier of: (ai) 10 seven (7) Days after CM/GC has received the information constituting the basis for the claim, or (bii) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (cii) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 6.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. Any reduction in the GMP will not be included in the cost savings described in Section 5.8. 8.1.5 6.2.5 CM/GC shall work with Engineer of Record to reconcile all differences in its GMP Change Request with the Engineer of Record within seven Days (7) days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.in

Appears in 1 contract

Samples: Construction Manager/General Cm/Gc Agreement

AutoNDA by SimpleDocs

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then only in accordance with the following procedure: 8.1.1 CM/GC 7.2.1 CM AT RISK shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GCCM AT RISK, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC CM AT RISK shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM AT RISK’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 CM/GC 7.2.3 CM AT RISK shall submit its GMP Change Requests as soon as possible, and CM/GC CM AT RISK shall not be entitled to claim a GMP increase unless CM/GC CM AT RISK submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 Days after CM/GC CM AT RISK has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC CM AT RISK intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's CM AT RISK’s signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's ’s basis for such request, which may include, for example, reduction of the CM/GC's Contingency CM AT RISK’s construction contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 CM/GC 7.2.5 CM AT RISK shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC CM AT RISK and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC CM AT RISK shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC CM AT RISK claim for a GMP increase.

Appears in 1 contract

Samples: Contract for Construction Manager at Risk

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they changes are a result of an evolution of the design documents (with any change in cost to be covered by contingency) or whether the changes represent a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Architect/Engineer of Record within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for examplebut are limited to, a reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Architect/Engineer of Record as needed to reconcile all differences in its GMP Change Request with the Architect/Engineer of Record within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Architect/Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s Architect/Engineer's position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's ’s signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's ’s basis for such request, which may include, for example, reduction of the CM/GC's ’s Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordArchitect’s position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record Architect within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Engineer of Record Architect to reconcile all differences in its GMP Change Request with the Engineer of Record Architect within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Engineer of Record Architect have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s Architect's position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only by Change Order and: (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this Contract, and then . Adjustments to the GMP will occur only in accordance with the following procedure: 8.1.1 CM/GC 6.2.1 Contractor shall review subsequent iterations of changes to the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GCContractor, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 6.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC Contractor shall deliver any such GMP Change Request to Engineer of Record and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in Contractor’s opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 CM/GC 6.2.3 Contractor shall submit its GMP Change Requests as soon as possible, and CM/GC Contractor shall not be entitled to claim a GMP increase unless CM/GC Contractor submitted a GMP Change Request to the Owner’s Authorized Representative and to Engineer of Record within the earlier of: (ai) 10 seven (7) Days after CM/GC Contractor has received the information constituting the basis for the claimClaim, or (bii) as to Work not yet bid or proposed, prior to submission of solicitations for such Work Work, and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC Contractor intends to claim a Scope Change; or and (ciii) in any event, prior to CM/GC's Contractor’s signing of a Change Order for the Scope Change. 8.1.4 The 6.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form from the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 CM/GC 6.2.5 Contractor shall work with Engineer of Record to reconcile all differences in its GMP Change Request with the Engineer of Record within seven (7) Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC Contractor and the Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of RecordEngineer’s position. CM/GC Contractor shall submit the Reconciled reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim Contractor Claim for a GMP increase. Owner retains the right to reject any such Claim in whole or in part, and to require additional information to substantiate the Claim.

Appears in 1 contract

Samples: Construction Manager/General Contractor Agreement

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they changes are a result of an evolution of the design documents (with any change in cost to be covered by Contingency) or whether the changes represent a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Engineer of Record Architect and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Architect/Engineer of Record within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or and (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change. 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for examplebut are limited to, a reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Architect/Engineer of Record as needed to reconcile all differences in its GMP Change Request with the Architect/Engineer of Record within seven Days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Architect/Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s Architect/Engineer's position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Construction Manager/General Contractor Contract

Adjustments to GMP. Adjustments to the GMP after execution of the GMP Amendment may be made only (i) in the event of Scope Changes or (ii) as otherwise expressly provided in this CM/GC Contract, and then only in accordance with the following procedure: 8.1.1 7.2.1 CM/GC shall review subsequent iterations of the Plans and Specifications as they are prepared to determine whether, in the opinion of CM/GC, they result in a Scope Change so that it can be determined if an adjustment to the GMP is warranted. 8.1.2 7.2.2 Changes to the GMP shall be initiated by written notice by one party to the other ("GMP Change Request"). CM/GC shall deliver any such GMP Change Request to Architect / Engineer of Record and the Owner’s Authorized Representative promptly after becoming aware of any Scope ChangeChange if, in CM/GC's opinion, it constitutes grounds for adjustment of the GMP. Any GMP Change Request shall include a proposal as to the appropriate GMP adjustment with respect to the Scope Change at issue. 8.1.3 7.2.3 CM/GC shall submit its GMP Change Requests as soon as possible, and CM/GC shall not be entitled to claim a GMP increase unless CM/GC submitted a GMP Change Request to the Owner’s Authorized Representative and to Architect / Engineer of Record within the earlier of: of (a) 10 30 Days after CM/GC has received the information constituting the basis for the claim, or (b) as to Work not yet bid or proposed, prior to submission of solicitations for such Work and as to Work already solicited, prior to commencement of the portion of the Work for which CM/GC intends to claim a Scope Change; or (c) in any event, prior to CM/GC's signing of a Change Order for the Scope Change.Work 8.1.4 The 7.2.4 Owner may, at any time, submit a GMP Change Request requesting a reduction of the GMP, which shall include the Owner's basis for such request, which may include, for example, reduction of the CM/GC's Contingency after further development of the Plans and Specifications that form the basis for the original GMP Amendment, and/or unused Allowances. 8.1.5 7.2.5 CM/GC shall work with Architect / Engineer of Record to reconcile all differences in its GMP Change Request with the Architect / Engineer of Record within seven Days (7) calendar days from the date of submission of the GMP Change Request. "Reconciled" means that the CM/GC and the Architect / Engineer of Record have verified that their assumptions about the various categories are the same, and that identifies they have identified the reason for differences in the GMP Change Request and the Engineer of Record’s Architect / Engineer's position. CM/GC shall submit the Reconciled GMP Change Request to the Owner, which submission shall be a condition to any CM/GC claim for a GMP increase.

Appears in 1 contract

Samples: Cm/Gc Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!