Common use of Application for Progress Clause in Contracts

Application for Progress. On or before the fifth (5th) day of each calendar month during the progress of the Work, Contractor shall submit to the Architect an itemized Application for Progress Payment for operations completed. Such application shall be notarized, if required, and supported by the following or such portion thereof as Architect requires: 1. The amount paid to the date of the Application to the Contractor, to all its Subcontractors, and all others furnishing labor, material, or equipment for its Contract; 2. The amount being requested under the Application for Payment by the Contractor on its own behalf and separately stating the amount requested on behalf of each of the Subcontractors and all others furnishing labor, material, and equipment under the Contract; 3. The balance that will be due to each of such entities after said payment is made; 4. A certification that the As-Built Drawings and Annotated Specifications are current;

Appears in 2 contracts

Samples: Bid Documents, Proposition 39 Energy Conservation and Energy Efficiency Services Agreement

AutoNDA by SimpleDocs

Application for Progress. On or before the fifth (5th) day of each calendar month during the progress of the Work, Contractor shall submit to the Architect an itemized Application for Progress Payment for operations completed. Such application shall be notarized, if required, and supported by the following or such portion thereof as Architect requires: 1. The amount paid to the date of the Application to the Contractor, to all its Subcontractors, and all others furnishing labor, material, or equipment for its Contract; 2. The amount being requested under the Application for Payment by the Contractor on its own behalf and separately stating the amount requested on behalf of each of the Subcontractors and all others furnishing labor, material, and equipment under the Contract; 3. The balance that will be due to each of such entities after said payment is made; 4. A certification that the As-Built Drawings and Annotated Specifications are current;

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Application for Progress. On or before the fifth (5th) day of each calendar month during the progress of the Work, Contractor shall submit to the Architect an itemized Application for Progress Payment for operations completed. Such application shall be notarized, if required, and supported by the following or such portion thereof as Architect requires:: G ENERAL CONDITIONS 1. The amount paid to the date of the Application to the Contractor, to all its Subcontractors, and all others furnishing labor, material, or equipment for its Contract; 2. The amount being requested under the Application for Payment by the Contractor on its own behalf and separately stating the amount requested on behalf of each of the Subcontractors and all others furnishing labor, material, and equipment under the Contract; 3. The balance that will be due to each of such entities after said payment is made; 4. A certification that the As-Built Drawings and Annotated Specifications are current;

Appears in 1 contract

Samples: Short Form Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!