Common use of Approval of Overall Project Schedule Clause in Contracts

Approval of Overall Project Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, and becomes a part of this Contract. The Overall Project Schedule shall govern the schedule of activities of the Contractor under this Contract

Appears in 36 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Approval of Overall Project Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, and becomes a part of this Contract. The Overall Project Schedule shall govern the schedule of activities of the Contractor CM/GC under this Contract

Appears in 2 contracts

Samples: Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.