Automatic Generation Control (AGC. (a) Prior to the Commercial Operation Date or, if applicable, prior to the Test Period, Seller, at its sole cost and expense, shall install AGC at the Storage Facility and shall maintain such AGC throughout the Delivery Term. Seller shall ensure that, throughout the Delivery Term, the SCADA signal is capable of functioning within the margin of error specified in the control system manufacturer’s Set Point(s) margin of error. Seller shall ensure that the Storage Facility’s AGC Remote/Local status is in “Remote” set-point control during normal operations. (b) Beginning on the Commercial Operation Date and throughout the Delivery Term, PGE shall have the right to direct the dispatch of the Storage Facility, via AGC control. (c) For each day during the Delivery Term, (i) PGE shall be responsible for, if it chooses, to register the Storage Facility in the Western Energy Imbalance Market (EIM) at its sole cost and expense and shall schedule and discharge the Storage Facility in accordance with the EIM’s rules, procedures and regulations, including those contained in the EIM OATT, and any applicable PGE business practices and (ii) PGE shall communicate directly to the Storage Facility in real time to dispatch the charging and discharging of the Storage Facility for the control modes identified in Exhibit L. This Section 3.4.2(c) will apply in the event the EIM is replaced, or any other market participation elected by PGE in accordance with Section 3.4.3(b). (d) PGE will have the right to charge the Storage Facility seven (7) days per week and twenty-four (24) hours per day (including NERC holidays) using energy from any source; provided that PGE shall pay for all such energy.
Appears in 3 contracts
Samples: Wholesale Renewable Power and Storage Capacity Purchase Agreement, Wholesale Renewable Power and Storage Capacity Purchase Agreement, Wholesale Renewable Power and Storage Capacity Purchase Agreement
Automatic Generation Control (AGC. (a) Prior to the Commercial Operation Date or, if applicable, prior to the Test Period, Seller, at its sole cost and expense, shall install AGC at the Storage Facility Project and shall maintain such AGC throughout the Delivery Term. Seller shall ensure that, throughout the Delivery Term, the SCADA signal is capable of functioning within the margin of error specified in the control system manufacturer’s Set Point(s) margin of error. Seller shall ensure that the Storage FacilityProject’s AGC Remote/Local status is in “Remote” set-point control during normal operations.
(b) Beginning on the Commercial Operation Date and throughout the Delivery Term, PGE Buyer shall have the right to direct the dispatch of the Storage FacilityESS, via AGC control, to its fullest capability subject to Section 5.9.
(c) For each day during the Delivery Term, (i) PGE Buyer shall be responsible for, if it chooses, to register the Storage Facility Project in the Western Energy Imbalance Market (EIM) at its sole cost and expense and shall schedule and discharge the Storage Facility Project in accordance with the EIM’s rules, procedures and regulations, including those contained in the EIM OATT, and any applicable PGE Buyer business practices and (ii) PGE Buyer shall communicate directly to the Storage Facility Project in real time to dispatch the charging and discharging of the Storage Facility ESS for the control modes identified in Exhibit L. This Section 3.4.2(c5.2(c) will apply in the event the EIM is replaced, or any other market participation elected by PGE Buyer in accordance with Section 3.4.3(b5.4(b).
(d) PGE Xxxxx will have the right to charge the Storage Facility seven (7) days per week and twenty-four (24) hours per day (including NERC holidays) using energy Energy from any source; provided that PGE Buyer shall pay for all such energyEnergy.
Appears in 2 contracts
Samples: Storage Capacity Agreement, Storage Capacity Agreement