BECOMING OPERATIONAL Sample Clauses
The 'Becoming Operational' clause defines the point at which a project, system, or facility is considered fully functional and ready for use. Typically, this clause outlines the specific criteria or tests that must be met, such as successful completion of commissioning procedures or achievement of performance benchmarks. By clearly establishing when operational status is achieved, the clause helps determine when responsibilities, warranties, or payment obligations commence, ensuring clarity and reducing disputes between parties.
BECOMING OPERATIONAL. 7.1 If directly connected to the NGC GB Transmission System NGC shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the NGC Construction Works excluding the Seven Year Statement Works shall be Commissioned and (2) the Seven Year Statement Works and Third Party Works shall be completed NGC shall forthwith notify the User in writing that the Connection Site shall become Operational.
7.2 If Embedded upon compliance by the User with the provisions of Clauses 5.1, 5.2 and 5.3 and subject, if NGC so requires, to the NGC Transmission Reinforcement Works [and/or works for the Modification] being carried out and/or the [New] Connection Site being Operational (any or all as appropriate) NGC shall forthwith notify the User ("Operational Notification") in writing that it has the right to use the NGC GB Transmission System. It is an express condition of this Construction Agreement that in no circumstances, will the User use or operate the User's Equipment without receiving the Operational Notification from NGC.
7.3 If, on completion of the User's Works in accordance with the terms of this Construction Agreement the Registered Capacity of the User's Equipment is less than [ ]MW, NGC shall automatically have the right to amend Clause 7 and Appendix C to the Bilateral Connection Agreement to reflect the actual Registered Capacity of the User's Equipment.
BECOMING OPERATIONAL. 7.1 If directly connected to the National Electricity Transmission System The Company shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Seven Year Statement Works [delete Seven Year Statement Works under the Connect and Manage Arrangements if these are not Enabling Works] shall be Commissioned and (2) [the Seven Year Statement Works and Third Party Works shall be completed The Company shall forthwith notify the User in writing that the Connection Site shall become Operational.] or
7.2 If Embedded upon compliance by the User with the provisions of Clauses 5.1, 5.2 and 5.3 and subject, if The Company so requires, to the Enabling Works [and/or works for the Modification] being carried out and/or the [New] Connection Site being Operational (any or all as appropriate) The Company shall forthwith notify the User ("Operational Notification") in writing that it has the right to use the National Electricity Transmission System. It is an express condition of this Construction Agreement that in no circumstances, will the User use or operate the User's Equipment without receiving the Operational Notification from The Company.]
7.3 If, on completion of the User's Works in accordance with the terms of this Construction Agreement the Registered Capacity of the User's Equipment is less than [ ]MW, The Company shall automatically have the right to amend Clause 7 and Appendix C to the Bilateral Connection Agreement to reflect the actual Registered Capacity of the User's Equipment.
BECOMING OPERATIONAL. 7.1 The Company shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Seven Year Statement Works shall be Commissioned and
(2) [the Seven Year Statement Works and Third Party Works shall be completed The Company shall forthwith notify the User in writing that the Connection Site shall become Operational.
BECOMING OPERATIONAL. 7.1 If directly connected to the GB Transmission System The Company shall connect and Energise the User's Equipment at the Connection Site during the course of and in accordance with the Commissioning Programme and thereafter upon compliance by the User with the provisions of Clause 5 and provided (1) the Construction Works excluding the Seven Year Statement Works shall be Commissioned and (2) the Seven Year Statement Works and Third Party Works shall be completed The Company shall forthwith notify the User in writing that the Connection Site shall become Operational.
7.2 If Embedded upon compliance by the User with the provisions of Clauses 5.1, 5.2 and 5.3 and subject, if The Company so requires, to the Transmission Reinforcement Works [and/or works for the Modification] being carried out and/or the [New] Connection Site being Operational (any or all as appropriate) The Company shall forthwith notify the User ("Operational Notification") in writing that it has the right to use the GB Transmission System. It is an express condition of this Construction Agreement that in no circumstances, will the User use or operate the User's Equipment without receiving the Operational Notification from The Company.