Boltdown Activities Sample Clauses
Boltdown Activities. These Boltdown Activities will be the responsibility of the Vendor only when the Owner has purchased the "Boltdown" service in Schedule 3A. Otherwise the Owner will be responsible for these activities. Prior to the Vendor performing these activities, all of the activities in Section 1.1 "Activities Required Prior to Boltdown" must be successfully completed.
a. Provide and install the conduit and cables for electricity (AC), Telco (T1, POTS etc.), heat strips (where necessary) and alarm cables from the Power Protection Cabinet (PPC) to the BTS. During Boltdown these cables are not to be terminated to the BTS, (Refer to Commissioning activities).
b. Provide all tools and test equipment required for installation.
c. Mount the BTS onto the pad, (ii) bolt the BTS to anchors, (iii) place batteries in trays (see Section A 1.8) and mount the antenna cable cover assemblies.
d. Remove any debris or refuse from the System Element Location resulting from BTS installation.