Breach by the User. If the User shall be in breach of any of the provisions of this Supplemental Agreement or of the provisions of the Master Agreement enforcing the provisions of the Grid Code (but subject always to Sub-Clauses 9.3 and 9.4 of the Master Agreement) and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of NGC or other Users or the NGC Transmission System or Users Systems then NGC may: (i) where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User to remedy the breach within 28 days after receipt of such notice or within any longer period agreed between NGC and the User, the agreement of NGC not to be unreasonably withheld or delayed; or (ii) where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to NGC not to repeat the breach.
Appears in 2 contracts
Samples: Connection and Use of System Documentation (Calenergy Co Inc), Connection and Use of System Documentation (Entergy London Capital Lp)
Breach by the User. If the User shall be in breach of any of the provisions of this Supplemental Agreement or of the provisions of the Master Agreement enforcing the provisions of the Grid Code (but subject always to Sub-Clauses 9.3 and 9.4 of the Master Agreement) and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of NGC or other Users or the NGC Transmission System or Users Systems then NGC may:
(i) where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User to remedy the breach within 28 days after receipt of such notice to remedy the breach or within any longer period agreed between NGC and the User, the agreement of NGC not to be unreasonably withheld or delayed; or
(ii) where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why NGC is of the reasonable opinion that the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to NGC not to repeat the breach.
Appears in 1 contract
Samples: Connection and Use of System Documentation (Entergy London Capital Lp)
Breach by the User. If the User shall be in breach of any of the provisions of this Supplemental Agreement or of the provisions of the Master Agreement enforcing the provisions of the Grid Code (but subject always to Sub-Clauses 9.3 and 9.4 of the Master Agreement) and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of NGC or other Users or the NGC Transmission System or Users Systems then NGC may:may:-
(i) where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User to remedy the breach within 28 days after receipt of such notice to remedy the breach or within any longer period agreed between NGC and the User, the agreement of NGC not to be unreasonably withheld or delayed; or
(ii) where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why NGC is of the reasonable opinion that the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to NGC not to repeat the breach.
Appears in 1 contract
Samples: Connection and Use of System Documentation (Calenergy Co Inc)
Breach by the User. If the User shall be in breach of any of the provisions of this Supplemental Agreement or of the provisions of the Master Agreement enforcing the provisions of the Grid Code (but subject always to Sub-Clauses 9.3 and 9.4 of the Master Agreement) and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of NGC or other Users or the NGC Transmission System or Users Systems then NGC may:
(i) where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User to remedy the breach within 28 days after receipt of such notice to remedy the breach or within any longer period agreed between NGC and the User, the agreement of NGC not to be unreasonably withheld or delayed; or
(ii) where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to NGC not to repeat the breach.
Appears in 1 contract
Samples: Connection and Use of System Documentation (Entergy London Capital Lp)
Breach by the User. If the User shall be in breach of any of the provisions of this Supplemental Agreement or of the provisions of the Master Agreement enforcing the provisions of the Grid Code (but subject always to Sub-Clauses 9.3 and 9.4 of the Master Agreement) and such breach causes or can reasonably be expected to cause a material adverse effect on the business or condition of NGC or other Users or the NGC Transmission System or Users Systems then NGC may:: -
(i) where the breach is capable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and requiring the User to remedy the breach within 28 days after receipt of such notice to remedy the breach or within any longer period agreed between NGC and the User, the agreement of NGC not to be unreasonably withheld or delayed; or
(ii) where the breach is incapable of remedy, give written notice to the User specifying in reasonable detail the nature of the breach and the reasons why the breach is incapable of remedy and requiring the User within 5 Business Days after receipt of such notice to undertake to NGC not to repeat the breach.
Appears in 1 contract
Samples: Connection and Use of System Documentation (Calenergy Co Inc)