Common use of BUILDING PERMITS/CERTIFICATES OF OCCUPANCY Clause in Contracts

BUILDING PERMITS/CERTIFICATES OF OCCUPANCY. A. No building permits shall be issued until the final plat is recorded, the streets (including curb and gutter installation) needed for access to lots where permits are requested are paved with the first lift of asphalt, and the sewer and water service utilities are tested and approved by the city engineer/designee. B. Prior to issuance of building permits, wetland buffer monuments shall be placed in accordance with the City’s zoning ordinance. Specifications for the monuments are available from the Community Development Department. C. Prior to issuance of building permits, written certification of the grading for the block where the building is to be located must be provided to the City. X. Xxxxxx of the terms of this contract by the Developer, including nonpayment of xxxxxxxx from the City, shall be grounds for denial of building permits, including lots sold to third parties, and the halting of all work in the plat. E. If building permits are issued prior to the acceptance of public improvements, the Developer assumes all liability and costs resulting in delays in completion of public improvements and damage to public improvements caused by the City, Developer, their contractors, subcontractors, materialmen, employees, agents, or third parties. No sewer and water connection permits may be issued until the streets needed for access have been paved with a bituminous surface and the utilities are tested and approved by the city engineer or designee.

Appears in 2 contracts

Samples: Development Contract, Development Contract

AutoNDA by SimpleDocs

BUILDING PERMITS/CERTIFICATES OF OCCUPANCY. A. No building permits shall be issued until the final plat is recorded, the streets (including curb and gutter installation) needed for access to lots where permits are requested are paved with the first lift of asphalt, and the sewer and water service utilities are tested and approved by the city engineer/designee. B. Prior to issuance of building permits, wetland buffer monuments shall be placed in accordance with the City’s zoning ordinance. Specifications for the monuments are available from the Community Development Department. C. Prior to issuance of building permits, written certification of the grading for the block where the building is to be located must be provided to the City. X. Xxxxxx of the terms of this contract by the Developer, including nonpayment of xxxxxxxx billings from the City, shall be grounds for denial of building permits, including lots sold to third parties, and the halting of all work in the plat. E. If building permits are issued prior to the acceptance of public improvements, the Developer assumes all liability and costs resulting in delays in completion of public improvements and damage to public improvements caused by the City, Developer, their contractors, subcontractors, materialmen, employees, agents, or third parties. No sewer and water connection permits may be issued until the streets needed for access have been paved with a bituminous surface and the utilities are tested and approved by the city engineer or designee.

Appears in 1 contract

Samples: Development Contract

BUILDING PERMITS/CERTIFICATES OF OCCUPANCY. A. No building permits shall be issued until the final plat is recorded, the streets (including curb and gutter installation) needed for access to lots where permits are requested are paved with the first lift of asphalt, and the sewer and water service utilities are tested and approved by the city engineer/designee. B. Prior to issuance of building permits, wetland buffer monuments shall be placed in accordance with the City’s zoning ordinance. Specifications for the monuments are available from the Community Development Department. C. Prior to issuance of building permits, written certification of the grading for the block where the building is to be located must be provided to the City. X. Xxxxxx D. Breach of the terms of this contract by the Developer, including nonpayment of xxxxxxxx from the City, shall be grounds for denial of building permits, including lots sold to third parties, and the halting of all work in the plat. E. If building permits are issued prior to the acceptance of public improvements, the Developer assumes all liability and costs resulting in delays in completion of public improvements and damage to public improvements caused by the City, Developer, their contractors, subcontractors, materialmen, employees, agents, or third parties. No sewer and water connection permits may be issued until the streets needed for access have been paved with a bituminous surface and the utilities are tested and approved by the city engineer or designee.

Appears in 1 contract

Samples: Development Contract

AutoNDA by SimpleDocs

BUILDING PERMITS/CERTIFICATES OF OCCUPANCY. A. No building permits shall be issued until the final plat is recorded, the streets (including curb and gutter installation) needed for access to lots where permits are requested are paved with the first lift of asphalt, and the sewer and water service utilities are tested and approved by the city engineer/designee. B. Prior to issuance of building permits, wetland buffer monuments shall be placed in accordance with the City’s zoning ordinance. Specifications for the monuments are available from the Community Development Department. C. Prior to issuance of building permits, written certification of the grading for the block where the building is to be located must be provided to the City. X. Xxxxxx of the terms of this contract by the Developer, including nonpayment of xxxxxxxx from the City, shall be grounds for denial of building permits, including lots sold to third parties, and the halting of all work in the plat. E. If building permits are issued prior to the acceptance of public improvements, the Developer assumes all liability and costs resulting in delays in completion of public improvements and damage to public improvements caused by the City, Developer, their contractors, subcontractors, materialmen, employees, agents, or third parties. No sewer and water connection permits may be issued until the streets needed for access have been paved with a bituminous surface and the utilities are tested and approved by the city engineer or designee.

Appears in 1 contract

Samples: Development Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!