By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or 2) upon seven days written notice if the Engineer’s Services are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.
Appears in 10 contracts
Samples: Short Form Agreement for Professional Services, Short Form Agreement for Professional Services, Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon Upon seven days written notice if the Engineer’s Services services for the Project are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result . Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in a termination by Engineer under Paragraph 5.01.I.3.01.A.1.b.
Appears in 9 contracts
Samples: Professional Services, Professional Services, Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result . Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in a termination by Engineer under Paragraph 5.01.I.3.01.A.1.b.
Appears in 7 contracts
Samples: Short Form of Agreement for Professional Services, Short Form of Agreement Between Owner and Engineer for Professional Services, Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.5.01.I. The Owner anticipates lead-based paint may be present and therefore shall not be consider a Constituent of Concern.
Appears in 6 contracts
Samples: Contract Agreement, Contract Proposal, Contract Proposal
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 6 contracts
Samples: Engineering Agreement, Engineering Agreement, Engineering Agreement
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I..
3) Engineer shall have no liability to Owner on account of such termination.
Appears in 4 contracts
Samples: Standard Form of Agreement Between Owner and Engineer, Standard Form of Agreement, Standard Form of Agreement Between Owner and Engineer
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as .
3) Engineer shall have no liability to Owner on account of such termination other than the result delivery of the presence at the Site any Documents in accordance with Section 6.03 of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.this Agreement.
Appears in 3 contracts
Samples: Construction Engineering Agreement, Construction Engineering Agreement, Construction Engineering Agreement
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as .
3) in the result event Engineer terminates this agreement for either of the presence at the Site above-specified reasons, Engineer shall have no liability to Owner on account of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 2 contracts
Samples: Professional Services, Professional Services
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, . Engineer shall have no liability to Owner on account of such termination as provided for in subparagraphs (1) or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.(2).
Appears in 2 contracts
Samples: Professional Services, Professional Services
By Engineer. 1) a. upon seven (7) days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) b. upon seven (7) days written notice if the Engineer’s Services are delayed for more than 90 ninety (90) days for reasons beyond Engineer’s control, or as the result of the presence at the Site Project site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.5.01.L.
c. Engineer shall have no liability to Owner on account of a termination for cause by Engineer.
Appears in 2 contracts
Samples: Professional Services, Professional Services
By Engineer. 1) upon seven days written notice if Engineer believes that Owner demands that is requesting Engineer to furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; : or
2) upon seven days written notice if the Engineer’s Services 's services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s 's control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 1 contract
Samples: Professional Services
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s 's responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services 's services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s 's control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 1 contract
Samples: Professional Services
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 1 contract
Samples: Short Form of Agreement Between Owner and Engineer for Professional Services
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services under a Task Order are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 1 contract
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.6.10.D.
3) Engineer shall have no liability to Owner on account of such termination.
Appears in 1 contract
Samples: Agreement Between Owner and Engineer for Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.6.10.
3) Engineer shall have no liability to Owner on account of such termination.
Appears in 1 contract
Samples: Proposal and Agreement
By Engineer. 1) upon seven days written notice if Owner demands Engineer believes that Engineer is being requested by Owner to furnish or perform services contrary to Engineer’s =s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services =s services for the Project are delayed or suspended for more than 90 days for reasons beyond Engineer’s =s control, or as the result .
3) Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.such termination.
Appears in 1 contract
Samples: Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; : or
2) upon seven days written notice if the Engineer’s Services services for the Project are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result . Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in a termination by Engineer under Paragraph 5.01.I.3.01.A.1.b.
Appears in 1 contract
Samples: Professional Services
By Engineer. 1) a. upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; oror
2) b. upon seven days written notice if the Engineer’s Services services under a Task Order are delayed or suspended for more than 90 cumulative days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I..
Appears in 1 contract
Samples: Agreement Between Owner and Engineer for Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I.3.03.I.
Appears in 1 contract
Samples: Professional Services Agreement
By Engineer. 1) upon seven fourteen days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven fourteen days written notice if the Engineer’s Services services for the Project are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result . Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in a termination by Engineer under Paragraph 5.01.I.3.01.A.1.b.
Appears in 1 contract
Samples: Professional Services
By Engineer. 1) upon seven days written notice if Owner demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s Services for the Project are delayed for more than 90 days for reasons beyond Engineer’s control, or as the result . Engineer shall have no liability to Owner on account of the presence at the Site of undisclosed Constituents of Concern, as set forth in a termination for cause by Engineer under Paragraph 5.01.I.3.01.A.1.b.
Appears in 1 contract
By Engineer. 1) a. upon seven days written notice if Owner Client demands that Engineer furnish or perform services contrary to Engineer’s responsibilities as a licensed professional; or
2) b. upon seven days written notice if the Engineer’s Services are delayed for more than 90 30 days for reasons beyond Engineer’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern, as set forth in Paragraph 5.01.I..
Appears in 1 contract