Common use of CHANGED CONDITION Clause in Contracts

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 6 contracts

Samples: Operational Services Contract, Operational Services Agreement, Operational Services Agreement

AutoNDA by SimpleDocs

CHANGED CONDITION. 10.01 10.1 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Landmark Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 3 contracts

Samples: Operational Services Contract, Operational Services Contract, Operational Services Contract

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Ministry Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 2 contracts

Samples: Operational Services Contract, Operational Services Contract

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Ministry Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 2 contracts

Samples: Operational Services Contract, Operational Services Contract

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Chinook Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 1 contract

Samples: Operational Services Contract

AutoNDA by SimpleDocs

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Representative Silvicon shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 1 contract

Samples: Operational Services Contract

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative and the Company Silvicon Services Inc. Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 1 contract

Samples: Operational Services Contract

CHANGED CONDITION. 10.01 If a Changed Condition occurs during the course of the Work, the following applies: (a) The Parties shall immediately advise each other of particulars of the Changed Condition and the Contractor Representative Representative, and the Company Ministry Representative shall meet to attempt to deal with the condition. (b) If the Changed Condition is so substantial that amending the Agreement to deal with the change would change the essential nature of the Work, then either Party may elect not to proceed with the Work any further and the contract shall be brought to an end. If either Party so elects, the Contractor shall be entitled to receive payment for any Work which the Contractor has satisfactorily completed, and shall be entitled to no further payment.

Appears in 1 contract

Samples: Operational Services Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!