Changes in Project Schedule Clause Samples
Changes in Project Schedule. 2.3.1 Changes in Project Schedule that increase the Estimated Cost must be approved by City in writing in accordance with Section 3.3.3.
2.3.2 Changes in Project Schedule that do not increase the Estimated Cost may be approved by the engineer designated by City’s Engineering and Capital Projects Department, which shall be responsible for review and approval of the progress of, and changes to the Project (Resident Engineer); provided, however, that the Project is still completed in accordance with the Financing Plan (including any associated phasing plans).
Changes in Project Schedule. All changes in the Project Schedule, including dates and substance, must be approved by the Project Manager in writing.
Changes in Project Schedule. Tenant shall submit to Landlord’s Representatives for review in connection with each Stage of Construction and during the course of construction, any material revisions or changes to the Project Schedule, subject to Force Majeure.
Changes in Project Schedule. 2.3.1 Changes in the Project Schedule that increase the Estimated Cost must be approved by City in writing in accordance with Section 3.3.3.
2.3.2 Changes in the Project Schedule that do not increase the Estimated Cost may be approved by the engineer designated by the City’s Public Works Department (Responsible Department), which shall be responsible for review and approval of the progress of, and changes to, the Project (Resident Engineer); provided, however, that the Project is still completed in accordance with the Financing Plan (including any associated phasing plans) and all conditions of approval including, but not limited to the VTM and the VTM Conditions.